Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work
- Item number
- 18.9.9
- Analysis basis
- 10 metre
- Priced inputs
- 5
- Derived rate
- ₹3,271.70/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.9.9 (Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work 100 mm nominal dia Pipes) is derived from 5 priced inputs for 10 metre and works out to ₹3,271.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 30 x P / 100
- Trenching and refilling etc.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8644 | MAT | Chlorinated Polyvinyl - chloride (CPVC) pipe 100 mm nominal dia | metre | 10 | 1,598.00 | 15,980.00 |
| 0116 | LAB | Fitter (grade 1) | day | 0.37 | 897.00 | 331.89 |
| 0114 | LAB | Beldar | day | 0.97 | 736.00 | 713.92 |
| 0114 | LAB | Beldar | day | 0.8 | 736.00 | 588.80 |
| 0115 | LAB | Coolie | day | 0.8 | 736.00 | 588.80 |
- Add 30% for fittings and wastage etc. on (P)
- +4,794.00
- TOTAL
- 22,997.41
- Add 1 % Water charges on “W”
- +229.97
- TOTAL
- 23,227.38
- Add GST on “X” (multiplying factor 0.2127)
- +4,940.46
- TOTAL
- 28,167.84
- Add 15% CPOH on “Y”
- +4,225.18
- TOTAL
- 32,393.02
- Add Cess @ 1% on “Z”
- +323.93
- Cost of 10 metre
- 32,716.95
- Cost of 1 metre
- 3,271.70
- SAY
- ₹3,271.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1425
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1425. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.