CPWD Analysis of Rates · Water Supply

Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work

150 mm nominal dia Pipes

Item number
18.9.10
Analysis basis
Details of cost for 10 metre
Priced inputs
5
Derived rate
6,822.70 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.9.10 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work 150 mm nominal dia Pipes — is derived from 5 priced inputs for 10 metre and works out to ₹6,822.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 30 x P / 100
  • Trenching and refilling etc.
CodeInputUnitQuantityRate (INR)Amount (INR)
8645Chlorinated Polyvinyl - chloride (CPVC) pipe 150 mm nominal diaMaterialmetre103,426.0034,260.00
0116Fitter (grade 1)Labourday0.58897.00520.26
0114BeldarLabourday1.54736.001,133.44
0114BeldarLabourday1.2736.00883.20
0115CoolieLabourday1.2736.00883.20
Add 30% for fittings and wastage etc. on (P)
10,278.00
TOTAL
47,958.10
Add 1 % Water charges on “W”
479.58
TOTAL
48,437.68
Add GST on “X” (multiplying factor 0.2127)
10,302.69
TOTAL
58,740.37
Add 15% CPOH on “Y”
8,811.06
TOTAL
67,551.43
Add Cess @ 1% on “Z”
675.51
Cost of 10 metre
68,226.94
Cost of 1 metre
6,822.69
Say
6,822.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1425. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.