Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work

150 mm nominal dia Pipes
Item number
18.9.10
Analysis basis
10 metre
Priced inputs
5
Derived rate
₹6,822.70/ METRE
D-01/RATE ANALYSISITEM 18.9.10

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.9.10 (Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. External work 150 mm nominal dia Pipes) is derived from 5 priced inputs for 10 metre and works out to ₹6,822.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 30 x P / 100
  • Trenching and refilling etc.
ANALYSIS OF RATES · ITEM 18.9.10DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8645MATChlorinated Polyvinyl - chloride (CPVC) pipe 150 mm nominal diametre103,426.0034,260.00
0116LABFitter (grade 1)day0.58897.00520.26
0114LABBeldarday1.54736.001,133.44
0114LABBeldarday1.2736.00883.20
0115LABCoolieday1.2736.00883.20
BUILD-UP TO RATE
Add 30% for fittings and wastage etc. on (P)
+10,278.00
TOTAL
47,958.10
Add 1 % Water charges on “W”
+479.58
TOTAL
48,437.68
Add GST on “X” (multiplying factor 0.2127)
+10,302.69
TOTAL
58,740.37
Add 15% CPOH on “Y”
+8,811.06
TOTAL
67,551.43
Add Cess @ 1% on “Z”
+675.51
Cost of 10 metre
68,226.94
Cost of 1 metre
6,822.69
SAY
₹6,822.70
D-02/SOURCEPRINTED PAGE 1425
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1425

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1425. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.