CPWD Analysis of Rates · Water Supply
Making chases up to 7.5x7.5 cm in walls including making good and finishing with matching surface after housing G.I. pipe etc
- Item number
- 18.78
- Analysis basis
- Details of cost for 10 metres
- Priced inputs
- 4
- Derived rate
- ₹202.90 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.78 — Making chases up to 7.5x7.5 cm in walls including making good and finishing with matching surface after housing G.I. pipe etc — is derived from 4 priced inputs for 10 metres and works out to ₹202.90 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Labour for making chases
- Cement concrete 1:3:6 (1 cement : 3
- coarse sand : 6 graded stone aggregate
- 20 mm nominal size)
- 0.075x0.075x10 m = 0.05625 cum
- Les 33% for pipe etc. = (-) 0.01856 cum
- = 0.03769 cum Say 0.04 cum
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0123 | Mason 1st classMason 1st classLabour | day | 0.25 | 897.00 | 224.25 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.25 | 816.00 | 204.00 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
| Rate as per item no 4.2.5 of SH : Concrete workRate as per item 4.2.5Sub-analysis | cum | 0.04 | 9,311.40 | 372.46 |
- TOTAL
- 1,536.71
- Add 1 % Water charges on “W-A”
- 11.64
- TOTAL
- 1,548.35
- Add GST on “X-A” (multiplying factor 0.2127)
- 250.11
- TOTAL
- 1,798.46
- Add 15% CPOH on “Y-A”
- 213.90
- TOTAL
- 2,012.36
- Add Cess @ 1% on “Z-A”
- 16.40
- Cost of 10 metre
- 2,028.76
- Cost of 1 metre
- 202.88
- Say
- 202.90
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1567. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.