CPWD Analysis of Rates · Water Supply
Making hole up to 20x20 cm and embedding pipes up to 150 mm diameter in masonry and filling with cement concrete 1:3:6 (1 cement : 3 coarse sand: 6 graded stone aggregate 20 mm nominal size) including disposal of malba
- Item number
- 18.79
- Analysis basis
- Details of cost for 10 metres
- Priced inputs
- 2
- Derived rate
- ₹209.20 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.79 — Making hole up to 20x20 cm and embedding pipes up to 150 mm diameter in masonry and filling with cement concrete 1:3:6 (1 cement : 3 coarse sand: 6 graded stone aggregate 20 mm nominal size) including disposal of malba — is derived from 2 priced inputs for 10 metres and works out to ₹209.20 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Cement concrete 1:3:6 (1 cement : 3
- coarse sand : 6 graded stone aggregate
- 20 mm nominal size)
- 0.2x0.2x10 m = 0.40 cum
- Les for pipe 3.14x(0.15)²/4x10 = (-) 0.177
- cum
- = 0.223 cum Say 0.22 cum
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per item no 4.2.5 of SH : Concrete workRate as per item 4.2.5Sub-analysis | cum | 0.22 | 9,311.40 | 2,048.51 | |
| 9999 | Disposal of malbaMaterial | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 2,079.20
- Add 1 % Water charges on “W-A”
- 0.31
- TOTAL
- 2,079.51
- Add GST on “X-A” (multiplying factor 0.2127)
- 6.59
- TOTAL
- 2,086.10
- Add 15% CPOH on “Y-A”
- 5.64
- TOTAL
- 2,091.74
- Add Cess @ 1% on “Z-A”
- 0.43
- Cost of 10 metre
- 2,092.17
- Cost of 1 metre
- 209.22
- Say
- 209.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1567. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works