Making hole up to 20x20 cm and embedding pipes up to 150 mm diameter in masonry and filling with cement concrete 1:3:6 (1 cement : 3 coarse sand: 6 graded stone aggregate 20 mm nominal size) including disposal of malba

Item number
18.79
Analysis basis
10 metres
Priced inputs
2
Derived rate
₹209.20/ METRE
D-01/RATE ANALYSISITEM 18.79

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.79 (Making hole up to 20x20 cm and embedding pipes up to 150 mm diameter in masonry and filling with cement concrete 1:3:6 (1 cement : 3 coarse sand: 6 graded stone aggregate 20 mm nominal size) including disposal of malba) is derived from 2 priced inputs for 10 metres and works out to ₹209.20 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement concrete 1:3:6 (1 cement : 3
  • coarse sand : 6 graded stone aggregate
  • 20 mm nominal size)
  • 0.2x0.2x10 m = 0.40 cum
  • Les for pipe 3.14x(0.15)²/4x10 = (-) 0.177
  • cum
  • = 0.223 cum Say 0.22 cum
ANALYSIS OF RATES · ITEM 18.79DETAILS OF COST FOR 10 METRES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 4.2.5 of SH : Concrete workRate as per item 4.2.5cum0.229,311.402,048.51
9999MATDisposal of malbaL.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
2,079.20
Add 1 % Water charges on “W-A”
+0.31
TOTAL
2,079.51
Add GST on “X-A” (multiplying factor 0.2127)
+6.59
TOTAL
2,086.10
Add 15% CPOH on “Y-A”
+5.64
TOTAL
2,091.74
Add Cess @ 1% on “Z-A”
+0.43
Cost of 10 metre
2,092.17
Cost of 1 metre
209.22
SAY
₹209.20
D-02/SOURCEPRINTED PAGE 1567
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1567

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1567. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.