Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes of Class K - 9 conforming to IS : 8329

500 mm dia Ductile Iron Double Flanged
Item number
18.73.9
Analysis basis
5 metre
Priced inputs
2
Derived rate
₹15,472.95/ METRE
D-01/RATE ANALYSISITEM 18.73.9

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.73.9 (Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes of Class K - 9 conforming to IS : 8329: 500 mm dia Ductile Iron Double Flanged) is derived from 2 priced inputs for 5 metre and works out to ₹15,472.95 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 500 mm dia. ductile iron pipes double
  • flanged
  • Weight of 1 m pipes = 147.900 Kg
  • Weight of 5 m pipes 147.900x5 = 739.50
  • Kg
ANALYSIS OF RATES · ITEM 18.73.9DETAILS OF COST FOR 5 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7694MATDuctile Iron Pipe Class K-9 flanges and welding 500mm diaDuctile Iron Pipe Class K-9 flanges and welding 500 mm diametre510,500.0052,500.00
SUBRate as per Item Number 18.23 of SH: Water SupplyRate as per item 18.23quintal7.4361.652,676.21
BUILD-UP TO RATE
TOTAL
55,176.21
Add 1 % Water charges on “W-A”
+525.00
TOTAL
55,701.21
Add GST on “X-A” (multiplying factor 0.2127)
+11,278.42
TOTAL
66,979.63
Add 15% CPOH on “Y-A”
+9,645.51
TOTAL
76,625.14
Add Cess @ 1% on “Z-A”
+739.49
Cost of 5 metre
77,364.63
Cost per metre
15,472.93
SAY
₹15,472.95
D-02/SOURCEPRINTED PAGE 1562
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1562

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1562. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.