CPWD Analysis of Rates · Water Supply
Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes of Class K - 9 conforming to IS : 8329
450 mm dia Ductile Iron Double Flanged
- Item number
- 18.73.8
- Analysis basis
- Details of cost for 5 metre
- Priced inputs
- 2
- Derived rate
- ₹10,136.10 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.73.8 — Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes of Class K - 9 conforming to IS : 8329: 450 mm dia Ductile Iron Double Flanged — is derived from 2 priced inputs for 5 metre and works out to ₹10,136.10 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 450 mm dia. ductile iron pipes double
- flanged
- Weight of 1 m pipes = 127.800 Kg
- Weight of 5 m pipes 127.800x5 = 639.00
- Kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7693 | Ductile Iron Pipe Class K-9 flanges and welding 450mm diaDuctile Iron Pipe Class K-9 flanges and welding 450 mm diaMaterial | metre | 5 | 6,800.00 | 34,000.00 |
| Rate as per Item Number 18.23 of SH: Water SupplyRate as per item 18.23Sub-analysis | quintal | 6.39 | 361.65 | 2,310.94 |
- TOTAL
- 36,310.94
- Add 1 % Water charges on “W-A”
- 340.00
- TOTAL
- 36,650.94
- Add GST on “X-A” (multiplying factor 0.2127)
- 7,304.12
- TOTAL
- 43,955.06
- Add 15% CPOH on “Y-A”
- 6,246.62
- TOTAL
- 50,201.68
- Add Cess @ 1% on “Z-A”
- 478.91
- Cost of 5 metre
- 50,680.59
- Cost per metre
- 10,136.12
- Say
- 10,136.10
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1562. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.