Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes of Class K - 9 conforming to IS : 8329
- Item number
- 18.73.10
- Analysis basis
- 5 metre
- Priced inputs
- 2
- Derived rate
- ₹19,925.30/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.73.10 (Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes of Class K - 9 conforming to IS : 8329: 600 mm dia Ductile Iron Double Flanged) is derived from 2 priced inputs for 5 metre and works out to ₹19,925.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 600 mm dia. ductile iron pipes double
- flanged
- Weight of 1 m pipes = 198.900 Kg
- Weight of 5 m pipes 198.900x5 = 994.50
- Kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7695 | MAT | Ductile Iron Pipe Class K-9 flanges and welding 600mm diaDuctile Iron Pipe Class K-9 flanges and welding 600 mm dia | metre | 5 | 13,500.00 | 67,500.00 |
| SUB | Rate as per Item Number 18.23 of SH: Water SupplyRate as per item 18.23 | quintal | 9.95 | 361.65 | 3,598.42 |
- TOTAL
- 71,098.42
- Add 1 % Water charges on “W-A”
- +675.00
- TOTAL
- 71,773.42
- Add GST on “X-A” (multiplying factor 0.2127)
- +14,500.82
- TOTAL
- 86,274.24
- Add 15% CPOH on “Y-A”
- +12,401.37
- TOTAL
- 98,675.61
- Add Cess @ 1% on “Z-A”
- +950.77
- Cost of 5 metre
- 99,626.38
- Cost per metre
- 19,925.28
- SAY
- ₹19,925.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1563
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1563. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.