R/DAR 2023

Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes of Class K - 9 conforming to IS : 8329

600 mm dia Ductile Iron Double Flanged
Item number
18.73.10
Analysis basis
5 metre
Priced inputs
2
Derived rate
₹19,925.30/ METRE
D-01/RATE ANALYSISITEM 18.73.10

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.73.10 (Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes of Class K - 9 conforming to IS : 8329: 600 mm dia Ductile Iron Double Flanged) is derived from 2 priced inputs for 5 metre and works out to ₹19,925.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 600 mm dia. ductile iron pipes double
  • flanged
  • Weight of 1 m pipes = 198.900 Kg
  • Weight of 5 m pipes 198.900x5 = 994.50
  • Kg
ANALYSIS OF RATES · ITEM 18.73.10DETAILS OF COST FOR 5 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7695MATDuctile Iron Pipe Class K-9 flanges and welding 600mm diaDuctile Iron Pipe Class K-9 flanges and welding 600 mm diametre513,500.0067,500.00
SUBRate as per Item Number 18.23 of SH: Water SupplyRate as per item 18.23quintal9.95361.653,598.42
BUILD-UP TO RATE
TOTAL
71,098.42
Add 1 % Water charges on “W-A”
+675.00
TOTAL
71,773.42
Add GST on “X-A” (multiplying factor 0.2127)
+14,500.82
TOTAL
86,274.24
Add 15% CPOH on “Y-A”
+12,401.37
TOTAL
98,675.61
Add Cess @ 1% on “Z-A”
+950.77
Cost of 5 metre
99,626.38
Cost per metre
19,925.28
SAY
₹19,925.30
D-02/SOURCEPRINTED PAGE 1563
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1563

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1563. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.