Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329
500 mm dia Ductile Iron Class K-7 pipes
- Item number
- 18.72.9
- Analysis basis
- Details of cost for 10 metre
- Priced inputs
- 2
- Derived rate
- ₹6,787.40 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.72.9 — Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329: 500 mm dia Ductile Iron Class K-7 pipes — is derived from 2 priced inputs for 10 metre and works out to ₹6,787.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 500mm dia. cast iron pipes (in 5.5 m
- lengths)
- Weight of 1 m pipes = 106.640 Kg
- Weight of 10m pipes 106.640x10
- = 1066.40 Kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7730 | Ductile Iron Class K7 pipe conforming to I.S. 8329 - 500mm diaDuctile Iron Class K- 7 pipe conforming to I.S. 8329 - 500 mm diaMaterial | metre | 10 | 4,500.00 | 45,000.00 |
| Rate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23Sub-analysis | quintal | 10.66 | 361.65 | 3,855.19 |
- TOTAL
- 48,855.19
- Add 1 % Water charges on “W-A”
- 450.00
- TOTAL
- 49,305.19
- Add GST on “X-A” (multiplying factor 0.2127)
- 9,667.22
- TOTAL
- 58,972.41
- Add 15% CPOH on “Y-A”
- 8,267.58
- TOTAL
- 67,239.99
- Add Cess @ 1% on “Z-A”
- 633.85
- Cost of 10 metre
- 67,873.84
- Cost per metre
- 6,787.38
- Say
- 6,787.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1539. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.