Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329
- Item number
- 18.72.10
- Analysis basis
- 10 metre
- Priced inputs
- 2
- Derived rate
- ₹8,965.95/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.72.10 (Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329: 600 mm dia Ductile Iron Class K-7 pipes) is derived from 2 priced inputs for 10 metre and works out to ₹8,965.95 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 600mm dia. cast iron pipes (in 5.5 m
- lengths)
- Weight of 1 m pipes = 138.61 Kg
- Weight of 10m pipes 138.61x10 =
- 1386.10 Kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7731 | MAT | Ductile Iron Class K7 pipe conforming to I.S. 8329 - 600mm diaDuctile Iron Class K- 7 pipe conforming to I.S. 8329 - 600 mm dia | metre | 10 | 5,950.00 | 59,500.00 |
| SUB | Rate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23 | quintal | 13.86 | 361.65 | 5,012.47 |
- TOTAL
- 64,512.47
- Add 1 % Water charges on “W-A”
- +595.00
- TOTAL
- 65,107.47
- Add GST on “X-A” (multiplying factor 0.2127)
- +12,782.21
- TOTAL
- 77,889.68
- Add 15% CPOH on “Y-A”
- +10,931.58
- TOTAL
- 88,821.26
- Add Cess @ 1% on “Z-A”
- +838.09
- Cost of 10 metre
- 89,659.35
- Cost per metre
- 8,965.94
- SAY
- ₹8,965.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1539
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1539. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.