Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329

700 mm dia Ductile Iron Class K-7 pipes
Item number
18.72.11
Analysis basis
10 metre
Priced inputs
2
Derived rate
₹11,566.35/ METRE
D-01/RATE ANALYSISITEM 18.72.11

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.72.11 (Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329: 700 mm dia Ductile Iron Class K-7 pipes) is derived from 2 priced inputs for 10 metre and works out to ₹11,566.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 700mm dia. cast iron pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 188.92 Kg
  • Weight of 10m pipes 188.92x10 =
  • 1889.20 Kg
ANALYSIS OF RATES · ITEM 18.72.11DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7732MATDuctile Iron Class K7 pipe conforming to I.S. 8329 - 700mm diaDuctile Iron Class K- 7 pipe conforming to I.S. 8329 - 700 mm diametre107,650.0076,500.00
SUBRate as per Item Number 18.23 of SH: Water SupplyRate as per item 18.23quintal18.89361.656,831.57
BUILD-UP TO RATE
TOTAL
83,331.57
Add 1 % Water charges on “W-A”
+765.00
TOTAL
84,096.57
Add GST on “X-A” (multiplying factor 0.2127)
+16,434.27
TOTAL
1,00,530.84
Add 15% CPOH on “Y-A”
+14,054.89
TOTAL
1,14,585.73
Add Cess @ 1% on “Z-A”
+1,077.54
Cost of 10 metre
1,15,663.27
Cost per metre
11,566.33
SAY
₹11,566.35
D-02/SOURCEPRINTED PAGE 1540
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1540

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1540. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.