Skip to main content
R/DAR 2023

Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329

450 mm dia Ductile Iron Class K-7 pipes
Item number
18.72.8
Analysis basis
10 metre
Priced inputs
2
Derived rate
₹6,163.35/ METRE
D-01/RATE ANALYSISITEM 18.72.8

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.72.8 (Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329: 450 mm dia Ductile Iron Class K-7 pipes) is derived from 2 priced inputs for 10 metre and works out to ₹6,163.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 450mm dia. cast iron pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 91.410 Kg
  • Weight of 10m pipes 91.410x10 = 914.10
  • Kg
ANALYSIS OF RATES · ITEM 18.72.8DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7729MATDuctile Iron Class K7 pipe conforming to I.S. 8329 - 450mm diaDuctile Iron Class K- 7 pipe conforming to I.S. 8329 - 450 mm diametre104,100.0041,000.00
SUBRate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23quintal9.14361.653,305.48
BUILD-UP TO RATE
TOTAL
44,305.48
Add 1 % Water charges on “W-A”
+410.00
TOTAL
44,715.48
Add GST on “X-A” (multiplying factor 0.2127)
+8,807.91
TOTAL
53,523.39
Add 15% CPOH on “Y-A”
+7,532.69
TOTAL
61,056.08
Add Cess @ 1% on “Z-A”
+577.51
Cost of 10 metre
61,633.59
Cost per metre
6,163.36
SAY
₹6,163.35
D-02/SOURCEPRINTED PAGE 1538
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1538

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1538. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.