Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329
- Item number
- 18.72.26
- Analysis basis
- 10 metre
- Priced inputs
- 2
- Derived rate
- ₹18,567.85/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.72.26 (Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329: 750 mm dia Ductile Iron Class K-9 pipes) is derived from 2 priced inputs for 10 metre and works out to ₹18,567.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 750mm dia. cast iron pipes (in 5.5 m
- lengths)
- Weight of 1 m pipes = 242.600 Kg
- Weight of 10m pipes 242.600x10 =
- 2426.00 Kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7662 | MAT | Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - 750mm diaDuctile Iron class K - 9 pipe Conforming to I.S. 8329 - 750 mm dia | metre | 10 | 12,435.00 | 1,24,350.00 |
| SUB | Rate as per Item Number 18.23 of SH: Water SupplyRate as per item 18.23 | quintal | 24.26 | 361.65 | 8,773.63 |
- TOTAL
- 1,33,123.63
- Add 1 % Water charges on “W-A”
- +1,243.50
- TOTAL
- 1,34,367.13
- Add GST on “X-A” (multiplying factor 0.2127)
- +26,713.74
- TOTAL
- 1,61,080.87
- Add 15% CPOH on “Y-A”
- +22,846.09
- TOTAL
- 1,83,926.96
- Add Cess @ 1% on “Z-A”
- +1,751.53
- Cost of 10 metre
- 1,85,678.49
- Cost per metre
- 18,567.85
- SAY
- ₹18,567.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1547
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1547. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.