Skip to main content
R/DAR 2023

Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329

800 mm dia Ductile Iron Class K-9 pipes
Item number
18.72.27
Analysis basis
10 metre
Priced inputs
2
Derived rate
₹18,891.20/ METRE
D-01/RATE ANALYSISITEM 18.72.27

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.72.27 (Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329: 800 mm dia Ductile Iron Class K-9 pipes) is derived from 2 priced inputs for 10 metre and works out to ₹18,891.20 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 800 mm dia. cast iron pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 267.100 Kg
  • Weight of 10m pipes 267.100x10 =
  • 2671.00 Kg
ANALYSIS OF RATES · ITEM 18.72.27DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7663MATDuctile Iron class K - 9 pipe Conforming to I.S. 8329 - 800mm diaDuctile Iron class K - 9 pipe Conforming to I.S. 8329 - 800 mm diametre1012,600.001,26,000.00
SUBRate as per Item Number 18.23 of SH: Water SupplyRate as per item 18.23quintal26.71361.659,659.67
BUILD-UP TO RATE
TOTAL
1,35,659.67
Add 1 % Water charges on “W-A”
+1,260.00
TOTAL
1,36,919.67
Add GST on “X-A” (multiplying factor 0.2127)
+27,068.20
TOTAL
1,63,987.87
Add 15% CPOH on “Y-A”
+23,149.23
TOTAL
1,87,137.10
Add Cess @ 1% on “Z-A”
+1,774.77
Cost of 10 metre
1,88,911.87
Cost per metre
18,891.19
SAY
₹18,891.20
D-02/SOURCEPRINTED PAGE 1548
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1548

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1548. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.