Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329
- Item number
- 18.72.25
- Analysis basis
- 10 metre
- Priced inputs
- 2
- Derived rate
- ₹17,431.60/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.72.25 (Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329: 700 mm dia Ductile Iron Class K-9 pipes) is derived from 2 priced inputs for 10 metre and works out to ₹17,431.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 700mm dia. cast iron pipes (in 5.5 m
- lengths)
- Weight of 1 m pipes = 217.540 Kg
- Weight of 10m pipes 217.540x10 =
- 2175.40 Kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7661 | MAT | Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - 700mm diaDuctile Iron class K - 9 pipe Conforming to I.S. 8329 - 700 mm dia | metre | 10 | 11,700.00 | 1,17,000.00 |
| SUB | Rate as per Item Number 18.23 of SH: Water SupplyRate as per item 18.23 | quintal | 21.754 | 361.65 | 7,867.33 |
- TOTAL
- 1,24,867.33
- Add 1 % Water charges on “W-A”
- +1,170.00
- TOTAL
- 1,26,037.33
- Add GST on “X-A” (multiplying factor 0.2127)
- +25,134.76
- TOTAL
- 1,51,172.09
- Add 15% CPOH on “Y-A”
- +21,495.71
- TOTAL
- 1,72,667.80
- Add Cess @ 1% on “Z-A”
- +1,648.00
- Cost of 10 metre
- 1,74,315.80
- Cost per metre
- 17,431.58
- SAY
- ₹17,431.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1547
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1547. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.