Skip to main content
R/DAR 2023

Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329

600 mm dia Ductile Iron Class K-9 pipes
Item number
18.72.24
Analysis basis
10 metre
Priced inputs
2
Derived rate
₹12,986.95/ METRE
D-01/RATE ANALYSISITEM 18.72.24

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.72.24 (Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329: 600 mm dia Ductile Iron Class K-9 pipes) is derived from 2 priced inputs for 10 metre and works out to ₹12,986.95 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 600mm dia. cast iron pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 168.680 Kg
  • Weight of 10m pipes 168.680x10 =
  • 1686.80 Kg
ANALYSIS OF RATES · ITEM 18.72.24DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7660MATDuctile Iron class K - 9 pipe Conforming to I.S. 8329 - 600mm diaDuctile Iron class K -9 pipe Conforming to I.S. 8329 - 600 mm diametre108,700.0087,000.00
SUBRate as per Item Number 18.23 of SH: Water SupplyRate as per item 18.23quintal16.868361.656,100.31
BUILD-UP TO RATE
TOTAL
93,100.31
Add 1 % Water charges on “W-A”
+870.00
TOTAL
93,970.31
Add GST on “X-A” (multiplying factor 0.2127)
+18,689.95
TOTAL
1,12,660.26
Add 15% CPOH on “Y-A”
+15,983.99
TOTAL
1,28,644.25
Add Cess @ 1% on “Z-A”
+1,225.44
Cost of 10 metre
1,29,869.69
Cost per metre
12,986.97
SAY
₹12,986.95
D-02/SOURCEPRINTED PAGE 1546
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1546

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1546. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.