Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329
- Item number
- 18.72.24
- Analysis basis
- 10 metre
- Priced inputs
- 2
- Derived rate
- ₹12,986.95/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.72.24 (Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS : 8329: 600 mm dia Ductile Iron Class K-9 pipes) is derived from 2 priced inputs for 10 metre and works out to ₹12,986.95 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 600mm dia. cast iron pipes (in 5.5 m
- lengths)
- Weight of 1 m pipes = 168.680 Kg
- Weight of 10m pipes 168.680x10 =
- 1686.80 Kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7660 | MAT | Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - 600mm diaDuctile Iron class K -9 pipe Conforming to I.S. 8329 - 600 mm dia | metre | 10 | 8,700.00 | 87,000.00 |
| SUB | Rate as per Item Number 18.23 of SH: Water SupplyRate as per item 18.23 | quintal | 16.868 | 361.65 | 6,100.31 |
- TOTAL
- 93,100.31
- Add 1 % Water charges on “W-A”
- +870.00
- TOTAL
- 93,970.31
- Add GST on “X-A” (multiplying factor 0.2127)
- +18,689.95
- TOTAL
- 1,12,660.26
- Add 15% CPOH on “Y-A”
- +15,983.99
- TOTAL
- 1,28,644.25
- Add Cess @ 1% on “Z-A”
- +1,225.44
- Cost of 10 metre
- 1,29,869.69
- Cost per metre
- 12,986.97
- SAY
- ₹12,986.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1546
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1546. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.