Skip to main content
R/DAR 2023

Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including testing of joints and the cost of rubber gasket

100 mm dia pipes
Item number
18.70.1
Analysis basis
50 Joints
Priced inputs
4
Derived rate
₹119.45/ JOINT
D-01/RATE ANALYSISITEM 18.70.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.70.1 (Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including testing of joints and the cost of rubber gasket: 100 mm dia pipes) is derived from 4 priced inputs for 50 Joints and works out to ₹119.45 per joint after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.70.1DETAILS OF COST FOR 50 JOINTS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7666MATRuber Gaskets Conforming to I.S 5382 of S.B.R quality 100mm diaRubber Gaskets Conforming to I.S 5382 of S.B.R quality 100 mm diaeach5035.001,750.00
0116LABFitter (grade 1)day1897.00897.00
0117LABAssistant Fitter or 2nd class Fitterday1816.00816.00
0114LABBeldarday1736.00736.00
BUILD-UP TO RATE
TOTAL
4,199.00
Add 1 % Water charges on “W”
+41.99
TOTAL
4,240.99
Add GST on “X” (multiplying factor 0.2127)
+902.06
TOTAL
5,143.05
Add 15% CPOH on “Y”
+771.46
TOTAL
5,914.51
Add Cess @ 1% on “Z”
+59.15
Cost of 50 joints
5,973.66
Cost of 1 joint
119.47
SAY
₹119.45
D-02/SOURCEPRINTED PAGE 1523
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1523

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1523. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.