Skip to main content
R/DAR 2023

Providing and laying D.I. Specials of Class K - 12 suitable for mechanical jointing as per IS: 9523

Above 600 mm dia
Item number
18.69.2
Analysis basis
1 quintal
Priced inputs
2
Derived rate
₹28,403.25/ QUINTAL
D-01/RATE ANALYSISITEM 18.69.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.69.2 (Providing and laying D.I. Specials of Class K - 12 suitable for mechanical jointing as per IS: 9523: Above 600 mm dia) is derived from 2 priced inputs for 1 quintal and works out to ₹28,403.25 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.69.2DETAILS OF COST FOR 1 QUINTAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7685MATDuctile Iron Specials suitable for mechancial jointing as per I.S. 9523 over 600mm diaDuctile Iron Specials suitable for mechanical jointing as per I.S. 9523 over 600 mm diaquintal119,500.0019,500.00
SUBRate as per Item Number 18.24 of SH: Water SupplyRate as per item 18.24quintal1661.85661.85
BUILD-UP TO RATE
TOTAL
20,161.85
Add 1 % Water charges on “W-A”
+195.00
TOTAL
20,356.85
Add GST on “X-A” (multiplying factor 0.2127)
+4,189.13
TOTAL
24,545.98
Add 15% CPOH on “Y-A”
+3,582.62
TOTAL
28,128.60
Add Cess @ 1% on “Z-A”
+274.67
Cost of 1 quintal
28,403.27
SAY
₹28,403.25
D-02/SOURCEPRINTED PAGE 1523
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1523

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1523. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.