Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including testing of joints and the cost of rubber gasket
- Item number
- 18.70.2
- Analysis basis
- 50 Joints
- Priced inputs
- 4
- Derived rate
- ₹192.85/ JOINT
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.70.2 (Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including testing of joints and the cost of rubber gasket: 150 mm dia pipes) is derived from 4 priced inputs for 50 Joints and works out to ₹192.85 per joint after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7668 | MAT | Ruber Gaskets Conforming to I.S 5382 of S.B.R quality 150mm diaRubber Gaskets Conforming to I.S 5382 of S.B.R quality 150 mm dia | each | 50 | 40.00 | 2,000.00 |
| 0116 | LAB | Fitter (grade 1) | day | 1.5 | 897.00 | 1,345.50 |
| 0117 | LAB | Assistant Fitter or 2nd class Fitter | day | 1.5 | 816.00 | 1,224.00 |
| 0114 | LAB | Beldar | day | 3 | 736.00 | 2,208.00 |
- TOTAL
- 6,777.50
- Add 1 % Water charges on “W”
- +67.78
- TOTAL
- 6,845.28
- Add GST on “X” (multiplying factor 0.2127)
- +1,455.99
- TOTAL
- 8,301.27
- Add 15% CPOH on “Y”
- +1,245.19
- TOTAL
- 9,546.46
- Add Cess @ 1% on “Z”
- +95.46
- Cost of 50 joints
- 9,641.92
- Cost of 1 joint
- 192.84
- SAY
- ₹192.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1524
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1524. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate