Skip to main content

CPWD Analysis of Rates · Water Supply

Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply and all CPVC plain & brass threaded fittings, including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and testing of joints complete as per direction of Engineer in Charge. Internal work - Exposed on wall

15 mm nominal dia Pipes

Item number
18.7.1
Analysis basis
Details of cost for 10 metre
Priced inputs
5
Derived rate
286.80 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.7.1 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply and all CPVC plain & brass threaded fittings, including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and testing of joints complete as per direction of Engineer in Charge. Internal work - Exposed on wall 15 mm nominal dia Pipes — is derived from 5 priced inputs for 10 metre and works out to ₹286.80 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 30 x P / 100
CodeInputUnitQuantityRate (INR)Amount (INR)
8636Chlorinated Polyvinyl - chloride (CPVC) pipe 15 mm nominal diaMaterialmetre1043.00430.00
9999Cement, sand and grit etc.MaterialL.S.2.732.276.20
0116Fitter (grade 1)Labourday0.33897.00296.01
0117Assistant Fitter or 2nd class FitterLabourday0.82816.00669.12
0114BeldarLabourday0.66736.00485.76
Add 30% for fittings and wastage etc. on (P)
129.00
TOTAL
2,016.09
Add 1 % Water charges on “W”
20.16
TOTAL
2,036.25
Add GST on “X” (multiplying factor 0.2127)
433.11
TOTAL
2,469.36
Add 15% CPOH on “Y”
370.40
TOTAL
2,839.76
Add Cess @ 1% on “Z”
28.40
Cost of 10 metre
2,868.16
Cost of 1 metre
286.82
Say
286.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1415. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works