Skip to main content
R/DAR 2023

Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply and all CPVC plain & brass threaded fittings, including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and testing of joints complete as per direction of Engineer in Charge. Internal work - Exposed on wall

20 mm nominal dia Pipes
Item number
18.7.2
Analysis basis
10 metre
Priced inputs
5
Derived rate
₹335.00/ METRE
D-01/RATE ANALYSISITEM 18.7.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.7.2 (Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply and all CPVC plain & brass threaded fittings, including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and testing of joints complete as per direction of Engineer in Charge. Internal work - Exposed on wall 20 mm nominal dia Pipes) is derived from 5 priced inputs for 10 metre and works out to ₹335.00 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 30 x P / 100
ANALYSIS OF RATES · ITEM 18.7.2DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8637MATChlorinated Polyvinyl - chloride (CPVC) pipe 20 mm nominal diametre1059.00590.00
9999MATCement, sand and grit etc.L.S.2.732.276.20
0116LABFitter (grade 1)day0.33897.00296.01
0117LABAssistant Fitter or 2nd class Fitterday0.98816.00799.68
0114LABBeldarday0.66736.00485.76
BUILD-UP TO RATE
Add 30% for fittings and wastage etc. on (P)
+177.00
TOTAL
2,354.65
Add 1 % Water charges on “W”
+23.55
TOTAL
2,378.20
Add GST on “X” (multiplying factor 0.2127)
+505.84
TOTAL
2,884.04
Add 15% CPOH on “Y”
+432.61
TOTAL
3,316.65
Add Cess @ 1% on “Z”
+33.17
Cost of 10 metre
3,349.82
Cost of 1 metre
334.98
SAY
₹335.00
D-02/SOURCEPRINTED PAGE 1416
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1416

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1416. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.