CPWD Analysis of Rates · Water Supply

Providing and laying D.I. specials of class K-12 suitable for push-on jointing as per IS : 9523

Above 600 mm dia

Item number
18.68.2
Analysis basis
Details of cost for 1 quintal
Priced inputs
2
Derived rate
26,696.10 / quintal

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.68.2 Providing and laying D.I. specials of class K-12 suitable for push-on jointing as per IS : 9523: Above 600 mm dia — is derived from 2 priced inputs for 1 quintal and works out to ₹26,696.10 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7683Ductile Iron K - 12 specials suitable for push on jointing over 600mm diaDuctile Iron K - 12 specials suitable for push on jointing over 600 mm diaMaterialquintal118,300.0018,300.00
Rate as per Item Number 18.24 of SH: Water SupplyRate as per item 18.24Sub-analysisquintal1661.85661.85
TOTAL
18,961.85
Add 1 % Water charges on “W-A”
183.00
TOTAL
19,144.85
Add GST on “X-A” (multiplying factor 0.2127)
3,931.33
TOTAL
23,076.18
Add 15% CPOH on “Y-A”
3,362.15
TOTAL
26,438.33
Add Cess @ 1% on “Z-A”
257.76
Cost of 1 quintal
26,696.09
Say
26,696.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1521. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works