Providing and laying D.I. specials of class K-12 suitable for push-on jointing as per IS : 9523
- Item number
- 18.68.1
- Analysis basis
- 1 quintal
- Priced inputs
- 2
- Derived rate
- ₹20,009.70/ QUINTAL
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.68.1 (Providing and laying D.I. specials of class K-12 suitable for push-on jointing as per IS : 9523: Up to 600 mm dia) is derived from 2 priced inputs for 1 quintal and works out to ₹20,009.70 per quintal after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7682 | MAT | Ductile Iron K - 12 specials suitable for push on jointing upto 600 mm diaDuctile Iron K - 12 specials suitable for push on jointing up to 600 mm dia | quintal | 1 | 13,600.00 | 13,600.00 |
| SUB | Rate as per Item Number 18.24 of SH: Water SupplyRate as per item 18.24 | quintal | 1 | 661.85 | 661.85 |
- TOTAL
- 14,261.85
- Add 1 % Water charges on “W-A”
- +136.00
- TOTAL
- 14,397.85
- Add GST on “X-A” (multiplying factor 0.2127)
- +2,921.65
- TOTAL
- 17,319.50
- Add 15% CPOH on “Y-A”
- +2,498.65
- TOTAL
- 19,818.15
- Add Cess @ 1% on “Z-A”
- +191.56
- Cost of 1 quintal
- 20,009.71
- SAY
- ₹20,009.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1521
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1521. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate