Providing and laying S&S C.I. Standard specials suitable for mechanical jointing as per IS : 13382

Above 300 mm dia
Item number
18.67.2
Analysis basis
1 quintal
Priced inputs
2
Derived rate
₹14,532.55/ QUINTAL
D-01/RATE ANALYSISITEM 18.67.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.67.2 (Providing and laying S&S C.I. Standard specials suitable for mechanical jointing as per IS : 13382 : Above 300 mm dia) is derived from 2 priced inputs for 1 quintal and works out to ₹14,532.55 per quintal after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.67.2DETAILS OF COST FOR 1 QUINTAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7711MATS&S Centrifugally (Spun) C.I. Pipe Specials suitabe for mechanical joint as per IS 13382 over 300mm diaS&S Centrifugally (Spun) C.I. Pipe Specials suitable for mechanical joint as per I.S. 13382 over 300 mm diaquintal19,750.009,750.00
SUBRate as per Item Number 18.24 of SH: Water SupplyRate as per item 18.24quintal1661.85661.85
BUILD-UP TO RATE
TOTAL
10,411.85
Add 1 % Water charges on “W-A”
+97.50
TOTAL
10,509.35
Add GST on “X-A” (multiplying factor 0.2127)
+2,094.56
TOTAL
12,603.91
Add 15% CPOH on “Y-A”
+1,791.31
TOTAL
14,395.22
Add Cess @ 1% on “Z-A”
+137.33
Cost of 1 quintal
14,532.55
SAY
₹14,532.55
D-02/SOURCEPRINTED PAGE 1521
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1521

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1521. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.