Providing and laying S&S C.I. Standard specials suitable for mechanical jointing as per IS : 13382
- Item number
- 18.67.2
- Analysis basis
- 1 quintal
- Priced inputs
- 2
- Derived rate
- ₹14,532.55/ QUINTAL
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.67.2 (Providing and laying S&S C.I. Standard specials suitable for mechanical jointing as per IS : 13382 : Above 300 mm dia) is derived from 2 priced inputs for 1 quintal and works out to ₹14,532.55 per quintal after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7711 | MAT | S&S Centrifugally (Spun) C.I. Pipe Specials suitabe for mechanical joint as per IS 13382 over 300mm diaS&S Centrifugally (Spun) C.I. Pipe Specials suitable for mechanical joint as per I.S. 13382 over 300 mm dia | quintal | 1 | 9,750.00 | 9,750.00 |
| SUB | Rate as per Item Number 18.24 of SH: Water SupplyRate as per item 18.24 | quintal | 1 | 661.85 | 661.85 |
- TOTAL
- 10,411.85
- Add 1 % Water charges on “W-A”
- +97.50
- TOTAL
- 10,509.35
- Add GST on “X-A” (multiplying factor 0.2127)
- +2,094.56
- TOTAL
- 12,603.91
- Add 15% CPOH on “Y-A”
- +1,791.31
- TOTAL
- 14,395.22
- Add Cess @ 1% on “Z-A”
- +137.33
- Cost of 1 quintal
- 14,532.55
- SAY
- ₹14,532.55
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1521
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1521. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate