R/DAR 2023

Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to IS:15801 UV stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings, including trenching, refilling & testing of joints complete as per direction of Engineer-inCharge. External work

PN - 16 Pipe, 40 mm OD (SDR-7.4)
Item number
18.6.4
Analysis basis
10 metre
Priced inputs
5
Derived rate
₹415.10/ METRE
D-01/RATE ANALYSISITEM 18.6.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.6.4 (Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to IS:15801 UV stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings, including trenching, refilling & testing of joints complete as per direction of Engineer-inCharge. External work PN - 16 Pipe, 40 mm OD (SDR-7.4)) is derived from 5 priced inputs for 10 metre and works out to ₹415.10 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIAL:
  • LABOUR:
  • Trenching and refilling etc.
ANALYSIS OF RATES · ITEM 18.6.4DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8629MATPoly propyleneRandom - Co - Polymer (PPR) pipes PN-16 (SDR 7.4) - 40 mm Outer diaPoly propylene- Random - Co - Polymer (PPR) pipes PN-16 (SDR 7.4) - 40 mm Outer diametre10130.001,300.00
0116LABFitter (grade 1)day0.16897.00143.52
0114LABBeldarday0.33736.00242.88
0114LABBeldarday0.66736.00485.76
0115LABCoolieday0.66736.00485.76
BUILD-UP TO RATE
Add 20% for fittings and wastage etc. on P, 20xP/100
+260.00
TOTAL
2,917.92
Add 1 % Water charges on “W”
+29.18
TOTAL
2,947.10
Add GST on “X” (multiplying factor 0.2127)
+626.85
TOTAL
3,573.95
Add 15% CPOH on “Y”
+536.09
TOTAL
4,110.04
Add Cess @ 1% on “Z”
+41.10
Cost of 10 metre
4,151.14
Cost of 1 metre
415.11
SAY
₹415.10
D-02/SOURCEPRINTED PAGE 1409
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1409

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1409. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.