Skip to main content
R/DAR 2023

Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to IS:15801 UV stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings, including trenching, refilling & testing of joints complete as per direction of Engineer-inCharge. External work

PN - 16 Pipe, 32 mm OD (SDR-7.4)
Item number
18.6.3
Analysis basis
10 metre
Priced inputs
5
Derived rate
₹316.25/ METRE
D-01/RATE ANALYSISITEM 18.6.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.6.3 (Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to IS:15801 UV stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings, including trenching, refilling & testing of joints complete as per direction of Engineer-inCharge. External work PN - 16 Pipe, 32 mm OD (SDR-7.4)) is derived from 5 priced inputs for 10 metre and works out to ₹316.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIAL:
  • LABOUR:
  • Trenching and refilling etc.
ANALYSIS OF RATES · ITEM 18.6.3DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8628MATPoly propyleneRandom - Co - Polymer (PPR) pipes PN-16 (SDR 7.4) - 32 mm Outer diaPoly propylene- Random - Co - Polymer (PPR) pipes PN-16 (SDR 7.4) - 32 mm Outer diametre1080.00800.00
0116LABFitter (grade 1)day0.12897.00107.64
0114LABBeldarday0.25736.00184.00
0114LABBeldarday0.66736.00485.76
0115LABCoolieday0.66736.00485.76
BUILD-UP TO RATE
Add 20% for fittings and wastage etc. on P, 20xP/100
+160.00
TOTAL
2,223.16
Add 1 % Water charges on “W”
+22.23
TOTAL
2,245.39
Add GST on “X” (multiplying factor 0.2127)
+477.59
TOTAL
2,722.98
Add 15% CPOH on “Y”
+408.45
TOTAL
3,131.43
Add Cess @ 1% on “Z”
+31.31
Cost of 10 metre
3,162.74
Cost of 1 metre
316.27
SAY
₹316.25
D-02/SOURCEPRINTED PAGE 1409
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1409

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1409. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.