Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to IS:15801 UV stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings, including trenching, refilling & testing of joints complete as per direction of Engineer-inCharge. External work
- Item number
- 18.6.2
- Analysis basis
- 10 metre
- Priced inputs
- 5
- Derived rate
- ₹265.05/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.6.2 (Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to IS:15801 UV stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings, including trenching, refilling & testing of joints complete as per direction of Engineer-inCharge. External work PN - 16 Pipe, 25 mm OD (SDR-7.4)) is derived from 5 priced inputs for 10 metre and works out to ₹265.05 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIAL:
- LABOUR:
- Trenching and refilling etc.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8627 | MAT | Poly propyleneRandom - Co - Polymer (PPR) pipes PN-16 (SDR 7.4) - 25 mm Outer diaPoly propylene- Random - Co - Polymer (PPR) pipes PN-16 (SDR 7.4) - 25 mm Outer dia | metre | 10 | 50.00 | 500.00 |
| 0116 | LAB | Fitter (grade 1) | day | 0.12 | 897.00 | 107.64 |
| 0114 | LAB | Beldar | day | 0.25 | 736.00 | 184.00 |
| 0114 | LAB | Beldar | day | 0.66 | 736.00 | 485.76 |
| 0115 | LAB | Coolie | day | 0.66 | 736.00 | 485.76 |
- Add 20% for fittings and wastage etc. on P, 20xP/100
- +100.00
- TOTAL
- 1,863.16
- Add 1 % Water charges on “W”
- +18.63
- TOTAL
- 1,881.79
- Add GST on “X” (multiplying factor 0.2127)
- +400.26
- TOTAL
- 2,282.05
- Add 15% CPOH on “Y”
- +342.31
- TOTAL
- 2,624.36
- Add Cess @ 1% on “Z”
- +26.24
- Cost of 10 metre
- 2,650.60
- Cost of 1 metre
- 265.06
- SAY
- ₹265.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1408
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1408. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.