Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to IS:15801 UV stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings, including trenching, refilling & testing of joints complete as per direction of Engineer-inCharge. External work

PN - 10 Pipe, 50 mm OD (SDR-11)
Item number
18.6.5
Analysis basis
10 metre
Priced inputs
5
Derived rate
₹450.95/ METRE
D-01/RATE ANALYSISITEM 18.6.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.6.5 (Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes conforming to IS:15801 UV stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply, including all PP - R plain & brass threaded polypropylene random fittings, including trenching, refilling & testing of joints complete as per direction of Engineer-inCharge. External work PN - 10 Pipe, 50 mm OD (SDR-11)) is derived from 5 priced inputs for 10 metre and works out to ₹450.95 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIAL:
  • LABOUR:
  • Trenching and refilling etc.
ANALYSIS OF RATES · ITEM 18.6.5DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8630MATPoly propyleneRandom - Co - Polymer (PPR) pipes PN-10 (SDR 11) - 50 mm Outer diaPoly propylene- Random - Co - Polymer (PPR) pipes PN-10 (SDR 11) - 50 mm Outer diametre10151.001,510.00
0116LABFitter (grade 1)day0.16897.00143.52
0114LABBeldarday0.33736.00242.88
0114LABBeldarday0.66736.00485.76
0115LABCoolieday0.66736.00485.76
BUILD-UP TO RATE
Add 20% for fittings and wastage etc. on P, 20xP/100
+302.00
TOTAL
3,169.92
Add 1 % Water charges on “W”
+31.70
TOTAL
3,201.62
Add GST on “X” (multiplying factor 0.2127)
+680.98
TOTAL
3,882.60
Add 15% CPOH on “Y”
+582.39
TOTAL
4,464.99
Add Cess @ 1% on “Z”
+44.65
Cost of 10 metre
4,509.64
Cost of 1 metre
450.96
SAY
₹450.95
D-02/SOURCEPRINTED PAGE 1410
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1410

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1410. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.