Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality

Item number
18.43
Analysis basis
one strainer
Priced inputs
5
Derived rate
₹960.30/ ONE STRAINER
D-01/RATE ANALYSISITEM 18.43

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.43 (Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of approved quality) is derived from 5 priced inputs for one strainer and works out to ₹960.30 per one strainer after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 18.43DETAILS OF COST FOR ONE STRAINER 1.5 LONG
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1882MATStrainer brass 40 mm dia 1.5 metre longeach1688.00688.00
9977MATCarriage to siteL.S.13.522.2730.69
0116LABFitter (grade 1)day0.17897.00152.49
0114LABBeldarday0.17736.00125.12
9999MATSundreis including hamp white lead etc.L.S.7.152.2716.23
BUILD-UP TO RATE
TOTAL
1,012.53
Add 1 % Water charges on “W”
+10.13
TOTAL
1,022.66
Add GST on “X” (multiplying factor 0.2127)
+217.52
TOTAL
1,240.18
Add 15% CPOH on “Y”
+186.03
TOTAL
1,426.21
Add Cess @ 1% on “Z”
+14.26
Cost of 1.5 metre
1,440.47
Cost of one metre
960.31
SAY
₹960.30
D-02/SOURCEPRINTED PAGE 1496
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1496

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1496. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.