Boring with 100 mm diameter casing pipe for hand pump / tubewell, in all soils except ordinary hard rocks requiring blasting, including removing the casing pipe after the hand pump / tube well is lowered and tested
- Item number
- 18.42.3
- Analysis basis
- 6m depth
- Priced inputs
- 5
- Derived rate
- ₹1,025.95/ M DEPTH
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.42.3 (Boring with 100 mm diameter casing pipe for hand pump / tubewell, in all soils except ordinary hard rocks requiring blasting, including removing the casing pipe after the hand pump / tube well is lowered and tested : Beyond 12 m and up to 18 m depth) is derived from 5 priced inputs for 6m depth and works out to ₹1,025.95 per m depth after water charges, GST, CPOH and cess. The full build-up is below.
- For boring and removing the pipeDepreciation @ 2% of the cost of casing
- pipe 6metre @ Rs. per metre
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0116 | LAB | Fitter (grade 1) | day | 0.75 | 897.00 | 672.75 |
| 0114 | LAB | Beldar | day | 4 | 736.00 | 2,944.00 |
| 0010 | MACH | Hire charges of Derrickmonkey rope and other accessoriesHire charges of Derrick monkey rope | day | 0.75 | 850.00 | 637.50 |
| 1472 | MAT | Casing pipe 100 mm dia | metre | 0.12 | 350.00 | 42.00 |
| 9999 | MAT | Sundries | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 4,326.94
- Add 1 % Water charges on “W”
- +43.27
- TOTAL
- 4,370.21
- Add GST on “X” (multiplying factor 0.2127)
- +929.54
- TOTAL
- 5,299.75
- Add 15% CPOH on “Y”
- +794.96
- TOTAL
- 6,094.71
- Add Cess @ 1% on “Z”
- +60.95
- Cost of 6 metre
- 6,155.66
- Cost of one metre
- 1,025.94
- SAY
- ₹1,025.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1495
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1495. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.