CPWD Analysis of Rates · Water Supply

Boring with 100 mm diameter casing pipe for hand pump / tubewell, in all soils except ordinary hard rocks requiring blasting, including removing the casing pipe after the hand pump / tube well is lowered and tested

Beyond 6 m and up to 12 m depth

Item number
18.42.2
Analysis basis
Details of cost for 6m depth
Priced inputs
5
Derived rate
884.85 / m depth

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.42.2 Boring with 100 mm diameter casing pipe for hand pump / tubewell, in all soils except ordinary hard rocks requiring blasting, including removing the casing pipe after the hand pump / tube well is lowered and tested : Beyond 6 m and up to 12 m depth — is derived from 5 priced inputs for 6m depth and works out to ₹884.85 per m depth after water charges, GST, CPOH and cess. The full build-up is below.

  • LABOUR for boring and removing the
  • pipeDepreciation @ 2% of the cost of casing
  • pipe 6metre @ Rs. per metre
CodeInputUnitQuantityRate (INR)Amount (INR)
0116Fitter (grade 1)Labourday0.62897.00556.14
0114BeldarLabourday3.5736.002,576.00
0010Hire charges of Derrick monkey rope and other accessoriesHire charges of Derrick monkey ropeMachineryday0.62850.00527.00
1472Casing pipe 100 mm diaMaterialmetre0.12350.0042.00
9999SundriesMaterialL.S.13.522.2730.69
TOTAL
3,731.83
Add 1 % Water charges on “W”
37.32
TOTAL
3,769.15
Add GST on “X” (multiplying factor 0.2127)
801.70
TOTAL
4,570.85
Add 15% CPOH on “Y”
685.63
TOTAL
5,256.48
Add Cess @ 1% on “Z”
52.56
Cost of 6 metre
5,309.04
Cost of one metre
884.84
Say
884.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1495. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.