Skip to main content
R/DAR 2023

Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well

Item number
18.44
Analysis basis
a depth
Priced inputs
5
Derived rate
₹546.00/ A DEPTH
D-01/RATE ANALYSISITEM 18.44

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.44 (Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well including cleaning and priming the tube well) is derived from 5 priced inputs for a depth and works out to ₹546.00 per a depth after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Carriage of 40mm pipe= pipe weight +
  • 2% for fiitings = 1.02 *10* 3.65 = 37 kg =
  • 0.037 tonne
ANALYSIS OF RATES · ITEM 18.44DETAILS OF COST FOR A DEPTH OF 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1549MATG.I. pipes 40 mm diametre10.2290.002,958.00
9999MATWhite lead, hamp and oil etc.L.S.6.762.2715.35
0116LABFitter (grade 1)day0.33897.00296.01
0114LABBeldarday0.75736.00552.00
9999MATSundriesL.S.7.252.2716.46
BUILD-UP TO RATE
TOTAL
3,837.82
Add 1 % Water charges on “W”
+38.38
TOTAL
3,876.20
Add GST on “X” (multiplying factor 0.2127)
+824.47
TOTAL
4,700.67
Add 15% CPOH on “Y”
+705.10
TOTAL
5,405.77
Add Cess @ 1% on “Z”
+54.06
Cost for 10 metre
5,459.83
Cost of one metre
545.98
SAY
₹546.00
D-02/SOURCEPRINTED PAGE 1496
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1496

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1496. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.