Painting G.I. pipes and fittings with synthetic enamel white paint with two coats over a ready mixed priming coat, both of approved quality for new work
- Item number
- 18.38.5
- Analysis basis
- 10 metre
- Priced inputs
- 3
- Derived rate
- ₹42.65/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.38.5 (Painting G.I. pipes and fittings with synthetic enamel white paint with two coats over a ready mixed priming coat, both of approved quality for new work : 40 mm diameter pipe) is derived from 3 priced inputs for 10 metre and works out to ₹42.65 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Perimeter = 0.1520 metre
- Area = 10x0.1520 sqm. = 1.520 sqm.
- Priming coatPainting two coats excluding priming coat
- with white paint on new work.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3 | sqm | 1.52 | 67.40 | 102.45 | |
| SUB | Rate as per item no 13.61.1 of SH : FinishingRate as per item 13.61.1 | sqm | 1.52 | 155.90 | 236.97 | |
| 9999 | MAT | Add for delay | L.S. | 26.91 | 2.27 | 61.09 |
- TOTAL
- 400.51
- Add 1 % Water charges on “W-A”
- +0.61
- TOTAL
- 401.12
- Add GST on “X-A” (multiplying factor 0.2127)
- +13.12
- TOTAL
- 414.24
- Add 15% CPOH on “Y-A”
- +11.22
- TOTAL
- 425.46
- Add Cess @ 1% on “Z-A”
- +0.86
- Cost of 10 metre
- 426.32
- Cost of one metre
- 42.63
- SAY
- ₹42.65
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1483
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1483. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.