Painting G.I. pipes and fittings with synthetic enamel white paint with two coats over a ready mixed priming coat, both of approved quality for new work

50 mm diameter pipe

Item number
18.38.6
Analysis basis
Details of cost for 10 metre
Priced inputs
3
Derived rate
51.00 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.38.6 Painting G.I. pipes and fittings with synthetic enamel white paint with two coats over a ready mixed priming coat, both of approved quality for new work : 50 mm diameter pipe — is derived from 3 priced inputs for 10 metre and works out to ₹51.00 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Perimeter = 0.1894 metre
  • Area = 10x0.1894 sqm. = 1.894 sqm.
  • Priming coatPainting two coats excluding priming coat
  • with white paint on new work.
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3Sub-analysissqm1.89467.40127.66
Rate as per item no 13.61.1 of SH : FinishingRate as per item 13.61.1Sub-analysissqm1.894155.90295.27
9999Add for delayMaterialL.S.26.912.2761.09
TOTAL
484.02
Add 1 % Water charges on “W-A”
0.61
TOTAL
484.63
Add GST on “X-A” (multiplying factor 0.2127)
13.12
TOTAL
497.75
Add 15% CPOH on “Y-A”
11.22
TOTAL
508.97
Add Cess @ 1% on “Z-A”
0.86
Cost of 10 metre
509.83
Cost of one metre
50.98
Say
51.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1484. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.