Painting G.I. pipes and fittings with synthetic enamel white paint with two coats over a ready mixed priming coat, both of approved quality for new work

50 mm diameter pipe
Item number
18.38.6
Analysis basis
10 metre
Priced inputs
3
Derived rate
₹51.00/ METRE
D-01/RATE ANALYSISITEM 18.38.6

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.38.6 (Painting G.I. pipes and fittings with synthetic enamel white paint with two coats over a ready mixed priming coat, both of approved quality for new work : 50 mm diameter pipe) is derived from 3 priced inputs for 10 metre and works out to ₹51.00 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Perimeter = 0.1894 metre
  • Area = 10x0.1894 sqm. = 1.894 sqm.
  • Priming coatPainting two coats excluding priming coat
  • with white paint on new work.
ANALYSIS OF RATES · ITEM 18.38.6DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3sqm1.89467.40127.66
SUBRate as per item no 13.61.1 of SH : FinishingRate as per item 13.61.1sqm1.894155.90295.27
9999MATAdd for delayL.S.26.912.2761.09
BUILD-UP TO RATE
TOTAL
484.02
Add 1 % Water charges on “W-A”
+0.61
TOTAL
484.63
Add GST on “X-A” (multiplying factor 0.2127)
+13.12
TOTAL
497.75
Add 15% CPOH on “Y-A”
+11.22
TOTAL
508.97
Add Cess @ 1% on “Z-A”
+0.86
Cost of 10 metre
509.83
Cost of one metre
50.98
SAY
₹51.00
D-02/SOURCEPRINTED PAGE 1484
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1484

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1484. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.