Painting G.I. pipes and fittings with synthetic enamel white paint with two coats over a ready mixed priming coat, both of approved quality for new work

32 mm diameter pipe
Item number
18.38.4
Analysis basis
10 metre
Priced inputs
3
Derived rate
₹36.35/ METRE
D-01/RATE ANALYSISITEM 18.38.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.38.4 (Painting G.I. pipes and fittings with synthetic enamel white paint with two coats over a ready mixed priming coat, both of approved quality for new work : 32 mm diameter pipe) is derived from 3 priced inputs for 10 metre and works out to ₹36.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Perimeter = 0.1334 metre
  • Area = 10x0.1334 sqm. = 1.334 sqm.
  • Priming coatPainting two coats excluding priming coat
  • with white paint on new work.
ANALYSIS OF RATES · ITEM 18.38.4DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3sqm1.33467.4089.91
SUBRate as per item no 13.61.1 of SH : FinishingRate as per item 13.61.1sqm1.334155.90207.97
9999MATAdd for delayL.S.20.282.2746.04
BUILD-UP TO RATE
TOTAL
343.92
Add 1 % Water charges on “W-A”
+0.46
TOTAL
344.38
Add GST on “X-A” (multiplying factor 0.2127)
+9.89
TOTAL
354.27
Add 15% CPOH on “Y-A”
+8.46
TOTAL
362.73
Add Cess @ 1% on “Z-A”
+0.65
Cost of 10 metre
363.38
Cost of one metre
36.34
SAY
₹36.35
D-02/SOURCEPRINTED PAGE 1483
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1483

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1483. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.