Painting G.I. pipes and fittings with synthetic enamel white paint with two coats over a ready mixed priming coat, both of approved quality for new work

20 mm diameter pipe
Item number
18.38.2
Analysis basis
10 metre
Priced inputs
3
Derived rate
₹23.25/ METRE
D-01/RATE ANALYSISITEM 18.38.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.38.2 (Painting G.I. pipes and fittings with synthetic enamel white paint with two coats over a ready mixed priming coat, both of approved quality for new work : 20 mm diameter pipe) is derived from 3 priced inputs for 10 metre and works out to ₹23.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Perimeter = 0.0845 metre
  • Area = 10x0.0845 sqm. = 0.845 sqm.
  • Priming coatPainting two coats excluding priming coat
  • with white paint on new work.
ANALYSIS OF RATES · ITEM 18.38.2DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3sqm0.84567.4056.95
SUBRate as per item no 13.61.1 of SH : FinishingRate as per item 13.61.1sqm0.845155.90131.74
9999MATAdd for delayL.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
219.38
Add 1 % Water charges on “W-A”
+0.31
TOTAL
219.69
Add GST on “X-A” (multiplying factor 0.2127)
+6.59
TOTAL
226.28
Add 15% CPOH on “Y-A”
+5.64
TOTAL
231.92
Add Cess @ 1% on “Z-A”
+0.43
Cost of 10 metre
232.35
Cost of one metre
23.24
SAY
₹23.25
D-02/SOURCEPRINTED PAGE 1482
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1482

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1482. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.