Painting G.I. pipes and fittings with synthetic enamel white paint with two coats over a ready mixed priming coat, both of approved quality for new work
- Item number
- 18.38.1
- Analysis basis
- 10 metre
- Priced inputs
- 3
- Derived rate
- ₹19.40/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.38.1 (Painting G.I. pipes and fittings with synthetic enamel white paint with two coats over a ready mixed priming coat, both of approved quality for new work : 15 mm diameter pipe) is derived from 3 priced inputs for 10 metre and works out to ₹19.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Perimeter = 0.0673 metre
- Area=10x0.0673m = 0.673sqm.
- Priming coatPainting two coats excluding priming coat
- with white paint on new work.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3 | sqm | 0.673 | 67.40 | 45.36 | |
| SUB | Rate as per item no 13.61.1 of SH : FinishingRate as per item 13.61.1 | sqm | 0.673 | 155.90 | 104.92 | |
| 9999 | MAT | Add for delay | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 180.97
- Add 1 % Water charges on “W-A”
- +0.31
- TOTAL
- 181.28
- Add GST on “X-A” (multiplying factor 0.2127)
- +6.59
- TOTAL
- 187.87
- Add 15% CPOH on “Y-A”
- +5.64
- TOTAL
- 193.51
- Add Cess @ 1% on “Z-A”
- +0.43
- Cost of 10 metre
- 193.94
- Cost of one metre
- 19.39
- SAY
- ₹19.40
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1481
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1481. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.