Constructing masonry Chamber 60x45x50 cm inside, in brick work in cement mortar 1:4 (1 cement : 4 coarse sand) for water meter complete with C.I. double flap surface box 400x200x200 mm (inside) with locking arrangement and RCC top slab 1:1.5:3 mix (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) , including necessary excavation, foundation concrete 1:5:10 ( 1 cement : 5 fine sand:10 graded stone aggregate 40 mm nominal size) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick, finished with a floating coat of neat cement complete as per standard design
- Item number
- 18.37.1
- Analysis basis
- one chamber
- Priced inputs
- 11
- Derived rate
- ₹9,698.55/ ONE CHAMBER
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.37.1 (Constructing masonry Chamber 60x45x50 cm inside, in brick work in cement mortar 1:4 (1 cement : 4 coarse sand) for water meter complete with C.I. double flap surface box 400x200x200 mm (inside) with locking arrangement and RCC top slab 1:1.5:3 mix (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) , including necessary excavation, foundation concrete 1:5:10 ( 1 cement : 5 fine sand:10 graded stone aggregate 40 mm nominal size) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick, finished with a floating coat of neat cement complete as per standard design : With common burnt clay F.P.S.(non modular) bricks of class designation 7.5) is derived from 11 priced inputs for one chamber and works out to ₹9,698.55 per one chamber after water charges, GST, CPOH and cess. The full build-up is below.
- (i) Earth work in excavation including
- refilling and disposal of surplus earth
- 1.21X1.06X0.85m = 1.09cum.
- (ii) Cement concrete 1:5:10 (1 Cement :
- 5 fine sand : 10 graded stone aggregate
- 40mm nominal size)
- 1.21x1.06x0.1m=0.128cum. Say 0.13 cum.
- (iii) Second class brick work in cement
- mortar 1:4 (1 Cement : 4 coarse sand) in
- foundations and plinth
- 3.02mx0.23mx0.50m=0.347cum.
- (iv) 12mm cement plaster 1:3 (1 Cement
- : 3 Coarse sand) finished with a floating
- coat of neat cement.
- 2.10mx0.50m=1.05sqm.
- 0.60mx0.45m=0.27sqm.
- Total=1.32sq
- (v) C.I. surface box 400x200x200mm
- (inside) with locking arrangement
- (vii) Cement concrete 1:1.5:3 (1 Cement
- : 1.5 Coarse sand ; 3 graded stone
- aggregate 20mm nominal size)
- in slab = 1.06mx0.91mx0.25m = 0.241
- cum.
- = (-)0.018 cum.
- = 0.223 cum. Say 0.22 cum.
- (viii)T.M.T. bars steel reinforcement for
- R.C.C work
- steel @ 80kg/cum.
- 0.223cum.x80kg/cum. = 17.84 kg.
- (x) Form work
- 0.60mx0.45m=0.27sqm.+
- 3.02mx0.25m=0.76sqm.
- Total = 1.03sqm.
- (xi)
- Say 0.35 cum.
- Less surface box 0.42x0.22mx0.2m
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no. 2.8.1 of SH: Earth workRate as per item 2.8.1 | cum | 1.09 | 260.30 | 283.73 | |
| SUB | Rate as per item No.2.25 of SH: Earth workRate as per item 2.25 | cum | 1.09 | 196.00 | 213.64 | |
| SUB | Rate as per item no 4.1.11 of SH : Concrete WorkRate as per item 4.1.11 | cum | 0.13 | 6,189.65 | 804.65 | |
| SUB | Rate as per item no 6.1.1 of SH : Brick WorkRate as per item 6.1.1 | cum | 0.35 | 7,370.65 | 2,579.73 | |
| SUB | Rate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1 | sqm | 1.32 | 449.55 | 593.41 | |
| 1307 | MAT | Surface box for water meter | each | 1 | 200.00 | 200.00 |
| 9977 | MAT | (vi) Carriage of C.I. surface box | L.S. | 13.52 | 2.27 | 30.69 |
| SUB | Rate as per item no. 5.1.2 of SH : RCC workRate as per item 5.1.2 | cum | 0.22 | 9,045.75 | 1,990.07 | |
| SUB | Rate as per item no. 5.22.6 of SH : RCC workRate as per item 5.22.6 | kg | 17.84 | 107.85 | 1,924.04 | |
| SUB | Rate as per item No.5.9.3 Of SH: RCCRate as per item 5.9.3 | sqm | 1.03 | 927.25 | 955.07 | |
| 9999 | MAT | Sundries | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 9,593.33
- Add 1 % Water charges on “W-A”
- +2.49
- TOTAL
- 9,595.82
- Add GST on “X-A” (multiplying factor 0.2127)
- +53.49
- TOTAL
- 9,649.31
- Add 15% CPOH on “Y-A”
- +45.75
- TOTAL
- 9,695.06
- Add Cess @ 1% on “Z-A”
- +3.51
- Cost of one manhole
- 9,698.57
- SAY
- ₹9,698.55
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1480
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1480. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.