Constructing masonry Chamber 90x90x100 cm inside, in brick work in cement mortar 1:4 (1 cement : 4 coarse sand) for sluice valve, with C.I. surface box 100 mm top diameter, 160 mm bottom diameter and 180 mm deep (inside) with chained lid and RCC top slab 1:1.5:3 mix (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size ), including necessary excavation, foundation concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size ) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick, finished with a floating coat of neat cement complete as per standard design
- Item number
- 18.34.1
- Analysis basis
- one chamber
- Priced inputs
- 11
- Derived rate
- ₹18,896.70/ ONE CHAMBER
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.34.1 (Constructing masonry Chamber 90x90x100 cm inside, in brick work in cement mortar 1:4 (1 cement : 4 coarse sand) for sluice valve, with C.I. surface box 100 mm top diameter, 160 mm bottom diameter and 180 mm deep (inside) with chained lid and RCC top slab 1:1.5:3 mix (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size ), including necessary excavation, foundation concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size ) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick, finished with a floating coat of neat cement complete as per standard design : With common burnt clay F.P.S.(non modular) bricks of class designation 7.5) is derived from 11 priced inputs for one chamber and works out to ₹18,896.70 per one chamber after water charges, GST, CPOH and cess. The full build-up is below.
- (i) Earth work in excavation including
- refilling and disposal of surplus earth
- 1.51X1.51X1.25 m = 2.85cum.
- (ii) Cement concrete 1:5:10 (1 Cement :
- 5 fine sand : 10 graded stone aggregate
- 40mm nominal size)
- 1.51x1.51x0.1m=0.228cum. Say 0.23 cum.
- (iii) Second class brick work in cement
- foundations and plinth foundations and
- plinth
- 4.52mx0.23mx1.00m=1.04cum.
- (iv) 12mm cement plaster 1:3 (1 Cement
- : 3 Coarse sand) finished with a floating
- coat of neat cement.
- 3.60mx1.00m=3.60sqm
- 0.90mx0.90m
- =0.81sqm.
- Total=4.41sqm.
- (v) C.I. surface box with chained lid.
- (vii) Cement concrete 1:1.5:3 (1 Cement
- : 1.5 Coarse sand ; 3 graded stone
- aggregate 20mm nominal size) in slab =
- 1.36mx1.36mx0.15m = 0.2774 cum.
- 0.7854x0.156mx0.156mx0.18m =
- (-)0.0034 cum.
- = 0.2740 cum. Say 0.27 cum.
- (viii)T.M.T. bars steel reinforcement for
- R.C.C work
- 0.274cum.x80kg/cum. = 21.92 kg.
- (ix) Form work
- 0.90mx0.90m=0.81sqm.+
- 4.52mx0.15m = 0.68 sqm.
- Total= 1.49 sqm.
- (x)
- Less surface box
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no. 2.8.1 of SH: Earth workRate as per item 2.8.1 | cum | 2.85 | 260.30 | 741.86 | |
| SUB | Rate as per item No.2.25 of SH: Earth workRate as per item 2.25 | cum | 2.85 | 196.00 | 558.60 | |
| SUB | Rate as per item no 4.1.11 of SH : Concrete WorkRate as per item 4.1.11 | cum | 0.23 | 6,189.65 | 1,423.62 | |
| SUB | Rate as per item no 6.1.1 of SH : Brick WorkRate as per item 6.1.1 | cum | 1.04 | 7,370.65 | 7,665.48 | |
| SUB | Rate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1 | sqm | 4.41 | 449.55 | 1,982.52 | |
| 1305 | MAT | Surface box for sluice valve | each | 1 | 200.00 | 200.00 |
| 9977 | MAT | (vi) Carriage of C.I. surface box | L.S. | 8.06 | 2.27 | 18.30 |
| SUB | Rate as per item no. 5.1.2 of SH : RCC workRate as per item 5.1.2 | cum | 0.27 | 9,045.75 | 2,442.35 | |
| SUB | Rate as per item no. 5.22.6 of SH : RCC workRate as per item 5.22.6 | kg | 21.92 | 107.85 | 2,364.07 | |
| SUB | Rate as per item No.5.9.3 Of SH: RCCRate as per item 5.9.3 | sqm | 1.49 | 927.25 | 1,381.60 | |
| 9999 | MAT | Sundries | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 18,796.70
- Add 1 % Water charges on “W-A”
- +2.37
- TOTAL
- 18,799.07
- Add GST on “X-A” (multiplying factor 0.2127)
- +50.83
- TOTAL
- 18,849.90
- Add 15% CPOH on “Y-A”
- +43.47
- TOTAL
- 18,893.37
- Add Cess @ 1% on “Z-A”
- +3.33
- Cost of one manhole
- 18,896.70
- SAY
- ₹18,896.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1475
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1475. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.