Skip to main content

CPWD Analysis of Rates · Water Supply

Constructing masonry Chamber 120x120x100 cm inside, in brick work in cement mortar 1:4 (1 cement : 4 coarse sand) for sluice valve, with C.I. surface box 100 mm top diameter, 160 mm bottom diameter and 180 mm deep ( inside) with chained lid and RCC top slab 1:1.5:3 mix (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size ), including necessary excavation, foundation concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick, finished with a floating coat of neat cement complete as per standard design

With common burnt clay F.P.S.(non modular) bricks of class designation 7.5

Item number
18.35.1
Analysis basis
Details of cost for one chamber
Priced inputs
11
Derived rate
26,163.40 / one chamber

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.35.1 Constructing masonry Chamber 120x120x100 cm inside, in brick work in cement mortar 1:4 (1 cement : 4 coarse sand) for sluice valve, with C.I. surface box 100 mm top diameter, 160 mm bottom diameter and 180 mm deep ( inside) with chained lid and RCC top slab 1:1.5:3 mix (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size ), including necessary excavation, foundation concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick, finished with a floating coat of neat cement complete as per standard design : With common burnt clay F.P.S.(non modular) bricks of class designation 7.5 — is derived from 11 priced inputs for one chamber and works out to ₹26,163.40 per one chamber after water charges, GST, CPOH and cess. The full build-up is below.

  • (i) Earth work in excavation including
  • refilling and disposal of surplus earth
  • 1.81X1.81X1.25M
  • (ii) Cement concrete 1:5:10 (1 Cement :
  • 5 fine sand : 10 graded stone aggregate
  • 40mm nominal size)
  • 1.81x1.81x0.1m=0.328cum. Say 0.33 cum.
  • (iii) Second class brick work in cement
  • mortar 1:4 (1 Cement : 4coarse sand) in
  • foundations and plinth
  • 5.72mx0.23mx1.00m=1.316cum.
  • (iv) 12mm cement plaster 1:3 (1 Cement
  • : 3 Coarse sand) finished with a floating
  • coat of neat cement.
  • 4.80mx1.00m=4.80sqm.
  • 1.20mx1.20m=1.44sqm.
  • Total=6.24sqm.
  • (v) C.I. surface box with chained lid
  • (vii) Cement concrete 1:1.5:3 (1 Cement
  • : 1.5 Coarse sand : 3 graded stone
  • aggregate 20mm nominal size)
  • in slab = 1.66mx1.66mx0.15m = 0.4133
  • cum.
  • 0.156mx0.18m = (-)0.0034 cum.
  • Total= 0.4099 cum. Say 0.41 cum.
  • (viii)T.M.T. bars steel reinforcement for
  • R.C.C work
  • 0.41cum.x80kg/cum. = 32.80kg.
  • (ix) Form work
  • 1.20mx1.20m=1.44sqm.+
  • 5.72mx0.15m=0.86 sqm.
  • Total = 2.30sqm.
  • (x)
  • Say 1.32 cum.
  • Less surface box 0.7854x0.156mx
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no. 2.8.1 of SH: Earth workRate as per item 2.8.1Sub-analysiscum4.1260.301,067.23
Rate as per item No.2.25 of SH: Earth workRate as per item 2.25Sub-analysiscum4.1196.00803.60
Rate as per item no 4.1.11 of SH : Concrete WorkRate as per item 4.1.11Sub-analysiscum0.336,189.652,042.58
Rate as per item no 6.1.1 of SH : Brick WorkRate as per item 6.1.1Sub-analysiscum1.327,370.659,729.26
Rate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1Sub-analysissqm6.24449.552,805.19
1305Surface box for sluice valveMaterialeach1200.00200.00
9977(vi) Carriage of C.I. surface boxMaterialL.S.8.062.2718.30
Rate as per item no. 5.1.2 of SH : RCC workRate as per item 5.1.2Sub-analysiscum0.419,045.753,708.76
Rate as per item no. 5.22.6 of SH : RCC workRate as per item 5.22.6Sub-analysiskg32.8107.853,537.48
Rate as per item No.5.9.3 Of SH: RCCRate as per item 5.9.3Sub-analysissqm2.3927.252,132.68
9999SundriesMaterialL.S.8.062.2718.30
TOTAL
26,063.38
Add 1 % Water charges on “W-A”
2.37
TOTAL
26,065.75
Add GST on “X-A” (multiplying factor 0.2127)
50.83
TOTAL
26,116.58
Add 15% CPOH on “Y-A”
43.47
TOTAL
26,160.05
Add Cess @ 1% on “Z-A”
3.33
Cost of one manhole
26,163.38
Say
26,163.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1477. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works