Skip to main content
R/DAR 2023

Constructing masonry Chamber 60x60x75 cm inside, in brick work in cement mortar 1:4 (1 cement : 4 coarse sand) for sluice valve, with C.I. surface box 100mm top diameter, 160 mm bottom diameter and 180 mm deep ( inside) with chained lid and RCC top slab 1:1.5:3 mix (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20mm nominal size ) , including necessary excavation, foundation concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick, finished with a floating coat of neat cement complete as per standard design

With common burnt clay F.P.S.(non modular) bricks of class designation 7.5
Item number
18.33.1
Analysis basis
one chamber
Priced inputs
11
Derived rate
₹10,862.40/ ONE CHAMBER
D-01/RATE ANALYSISITEM 18.33.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.33.1 (Constructing masonry Chamber 60x60x75 cm inside, in brick work in cement mortar 1:4 (1 cement : 4 coarse sand) for sluice valve, with C.I. surface box 100mm top diameter, 160 mm bottom diameter and 180 mm deep ( inside) with chained lid and RCC top slab 1:1.5:3 mix (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20mm nominal size ) , including necessary excavation, foundation concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick, finished with a floating coat of neat cement complete as per standard design : With common burnt clay F.P.S.(non modular) bricks of class designation 7.5) is derived from 11 priced inputs for one chamber and works out to ₹10,862.40 per one chamber after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (i) Earth work in excavation including
  • refilling and disposal of surplus earth
  • 1.21x1.21x1.00m=1.464cum.
  • (ii) Cement concrete 1:5:10 (1 Cement :
  • 5 fine sand : 10 graded stone aggregate
  • 40mm nominal size)
  • 1.21x1.21x0.1m=0.146cum. Say 0.15
  • cum.
  • (iii) Second class brick work in cement
  • mortar 1: 4(1 Cement : 4coarse sand) in
  • foundations and plinth
  • 3.32mx0.23mx0.75m=0.573cum.
  • (iv) 12mm cement plaster 1:3 (1 Cement
  • : 3 Coarse sand) finished with a floating
  • coat of neat cement.
  • 2.40x0.75=1.80sqm.
  • 0.60x0.60=0.36sqm.
  • Total = 2.16sqm.
  • (v) C.I. surface box with hinged cover
  • 100x100x75mm (inside)
  • (vi)
  • (vii) Cement concrete 1:1.5:3 (1 Cement
  • : 1.5 Coarse sand ; 3 graded stone
  • aggregate 20mm nominal size)
  • in slab = 1.06mx1.06mx0.15m = 0.1685
  • cum.
  • 0.7854x0.156mx0.156mx0.18 = (-)0.0034
  • cum.
  • = 0.1651 cum. Say 0.17 cum.
  • (viii)T.M.T. bars steel reinforcement for
  • R.C.C work
  • 0.165cum.x80kg/cum. = 13.2kg
  • (ix) Form work 0.60mx0.60m=0.36sqm.+
  • 3.32mx0.15m=0.50sqm.
  • = 0.86 sqm.
  • (x)
  • Say 1.46 cum.
  • Say 0.57 cum.
  • Less surface box 3.142/4xd2x0.18m --
ANALYSIS OF RATES · ITEM 18.33.1DETAILS OF COST FOR ONE CHAMBER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no. 2.8.1 of SH: Earth workRate as per item 2.8.1cum1.46260.30380.04
SUBRate as per item No.2.25 of SH: Earth WorkRate as per item 2.25cum1.46196.00286.16
SUBRate as per item no 4.1.11 of SH : Concrete WorkRate as per item 4.1.11cum0.156,189.65928.45
SUBRate as per item no 6.1.1 of SH : Brick WorkRate as per item 6.1.1cum0.577,370.654,201.27
SUBRate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1sqm2.16449.55971.03
1305MATSurface box for sluice valveeach1200.00200.00
9977MATCarriage of C.I. surface boxL.S.8.062.2718.30
SUBRate as per item no. 5.1.2 of SH : RCC workRate as per item 5.1.2cum0.179,045.751,537.78
SUBRate as per item no. 5.22.6 of SH : RCC workRate as per item 5.22.6kg13.2107.851,423.62
SUBRate as per item No.5.9.3 Of SH: RCCRate as per item 5.9.3sqm0.86927.25797.44
9999MATSundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
10,762.39
Add 1 % Water charges on “W-A”
+2.37
TOTAL
10,764.76
Add GST on “X-A” (multiplying factor 0.2127)
+50.83
TOTAL
10,815.59
Add 15% CPOH on “Y-A”
+43.47
TOTAL
10,859.06
Add Cess @ 1% on “Z-A”
+3.33
Cost of one manhole
10,862.39
SAY
₹10,862.40
D-02/SOURCEPRINTED PAGE 1474
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1474

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1474. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.