Constructing masonry Chamber 30x30x50 cm inside, in brick work in cement mortar 1:4 (1 cement :4 coarse sand) for stop cock, with C. I. surface box 100x100 x75 mm (inside) with hinged cover fixed in reinforced cement concrete slab 1:1.5:3 mix (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size), including necessary excavation, foundation concrete 1:5:10 ( 1 cement : 5 fine sand : 10 graded stone aggregate 40mm nominal size ) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12mm thick, finished with a floating coat of neat cement complete as per standard design

With common burnt clay F.P.S.(non modular) bricks of class designation 7.5
Item number
18.32.1
Analysis basis
one chamber
Priced inputs
10
Derived rate
₹1,992.60/ ONE CHAMBER
D-01/RATE ANALYSISITEM 18.32.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.32.1 (Constructing masonry Chamber 30x30x50 cm inside, in brick work in cement mortar 1:4 (1 cement :4 coarse sand) for stop cock, with C. I. surface box 100x100 x75 mm (inside) with hinged cover fixed in reinforced cement concrete slab 1:1.5:3 mix (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size), including necessary excavation, foundation concrete 1:5:10 ( 1 cement : 5 fine sand : 10 graded stone aggregate 40mm nominal size ) and inside plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12mm thick, finished with a floating coat of neat cement complete as per standard design : With common burnt clay F.P.S.(non modular) bricks of class designation 7.5) is derived from 10 priced inputs for one chamber and works out to ₹1,992.60 per one chamber after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (i) Earth work in excavation including
  • refilling and disposal of surplus earth
  • 0.68x0.68x0.65m=0.301cum.
  • (ii) Cement concrete 1:5:10 (1 Cement :
  • 5 fine sand : 10 graded stone aggregate
  • 40mm nominal size)
  • 0.68x0.68x0.075m=0.035cum. Say 0.04
  • cum.
  • (iii) Half brick masonry with FPS bricks of
  • class 7.5 in cement mortar 1:4 (1 Cement
  • : 4 coarse sand) in foundations and plinth
  • 1.66mx0.50m=0.83 sqm
  • (iv) 12mm cement plaster 1:3 (1 Cement
  • : 3 Coarse sand) finished with a floating
  • coat of neat cement.
  • 1.20x0.50=0.60sqm
  • 0.30x0.30=0.09sqm.
  • Total =0.69sqm. Say 0.70sqm.
  • (vi)
  • (vii) Cement concrete 1:1.5:3 (1 Cement
  • : 1.5 Coarse sand : 3 graded stone
  • aggregate 20mm nominal size) in slab =
  • 0.53mx0.53mx0.075m = 0.02107cum.
  • )0.00094 cum.
  • = 0.0201 cum. Say 0.02cum.
  • (viii)T.M.T. bars steel reinforcement for
  • R.C.C work
  • 0.02 cumx80kg/cum. = 1.60kg
  • Less surface box 0.112x0.112x0.076 =(-
ANALYSIS OF RATES · ITEM 18.32.1DETAILS OF COST FOR ONE CHAMBER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUB(Rate as per item no. 2.8.1 of SH: Earth work)Rate as per item 2.8.1cum0.3260.3078.09
SUBRate as per item No.2.25Rate as per item 2.25cum0.3196.0058.80
SUBRate as per item no 4.1.11 of SH : Concrete workRate as per item 4.1.11cum0.046,189.65247.59
SUBRate as per item no 6.12.2 of SH : Brick WorkRate as per item 6.12.2sqm0.83905.05751.19
SUBRate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1sqm0.7449.55314.69
1304MATSurface box for stop cockeach1120.00120.00
9977MATCarriage of C.I. surface boxL.S.1.432.273.25
SUBRate as per item no. 5.1.2 of SH : RCC workRate as per item 5.1.2cum0.029,045.75180.92
SUBRate as per item no. 5.22.6 of SH : RCC workRate as per item 5.22.6kg1.6107.85172.56
9999MATSundriesL.S.4.162.279.44
BUILD-UP TO RATE
TOTAL
1,936.53
Add 1 % Water charges on “W-A”
+1.33
TOTAL
1,937.86
Add GST on “X-A” (multiplying factor 0.2127)
+28.51
TOTAL
1,966.37
Add 15% CPOH on “Y-A”
+24.38
TOTAL
1,990.75
Add Cess @ 1% on “Z-A”
+1.87
Cost of one manhole
1,992.62
SAY
₹1,992.60
D-02/SOURCEPRINTED PAGE 1473
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1473

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1473. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.