Providing and fixing Polyethelene-AluminiumPolyethelene PE-AL-PE Composite Pressure Pipes conforming to IS - 15450, U.V. stabilized with carbon black having thermal stability for hot & cold water supply, capable to withstand temperature up to 80°C, including all special fittings of composite material (engineering plastic blend and brass inserts wherever required) e.g. elbows, tees, reducers, couplers & connectors etc., with trenching, refilling and testing of joints complete as per direction of the engineer in charge. External work
- Item number
- 18.3.3
- Analysis basis
- 10 metre
- Priced inputs
- 5
- Derived rate
- ₹340.85/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.3.3 (Providing and fixing Polyethelene-AluminiumPolyethelene PE-AL-PE Composite Pressure Pipes conforming to IS - 15450, U.V. stabilized with carbon black having thermal stability for hot & cold water supply, capable to withstand temperature up to 80°C, including all special fittings of composite material (engineering plastic blend and brass inserts wherever required) e.g. elbows, tees, reducers, couplers & connectors etc., with trenching, refilling and testing of joints complete as per direction of the engineer in charge. External work 2025 (25 mm OD ) pipe) is derived from 5 priced inputs for 10 metre and works out to ₹340.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 30 x P / 100
- Trenching and refilling etc.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8302 | MAT | 2025 mm PE-AL-PE Composit pressure pipe2025 mm PE-AL-PE Composite pressure pipe | metre | 10 | 95.00 | 950.00 |
| 0116 | LAB | Fitter (grade 1) | day | 0.08 | 897.00 | 71.76 |
| 0114 | LAB | Beldar | day | 0.16 | 736.00 | 117.76 |
| 0114 | LAB | Beldar | day | 0.66 | 736.00 | 485.76 |
| 0115 | LAB | Coolie | day | 0.66 | 736.00 | 485.76 |
- Add 30% for fittings and wastage etc. on (P)
- +285.00
- TOTAL
- 2,396.04
- Add 1 % Water charges on “W”
- +23.96
- TOTAL
- 2,420.00
- Add GST on “X” (multiplying factor 0.2127)
- +514.73
- TOTAL
- 2,934.73
- Add 15% CPOH on “Y”
- +440.21
- TOTAL
- 3,374.94
- Add Cess @ 1% on “Z”
- +33.75
- Cost of 10 metre
- 3,408.69
- Cost of 1 metre
- 340.87
- SAY
- ₹340.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1401
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1401. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.