Skip to main content
R/DAR 2023

Providing and fixing Polyethelene-AluminiumPolyethelene PE-AL-PE Composite Pressure Pipes conforming to IS - 15450, U.V. stabilized with carbon black having thermal stability for hot & cold water supply, capable to withstand temperature up to 80°C, including all special fittings of composite material (engineering plastic blend and brass inserts wherever required) e.g. elbows, tees, reducers, couplers & connectors etc., with trenching, refilling and testing of joints complete as per direction of the engineer in charge. External work

1620 (20 mm OD ) pipe
Item number
18.3.2
Analysis basis
10 metre
Priced inputs
5
Derived rate
₹289.10/ METRE
D-01/RATE ANALYSISITEM 18.3.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.3.2 (Providing and fixing Polyethelene-AluminiumPolyethelene PE-AL-PE Composite Pressure Pipes conforming to IS - 15450, U.V. stabilized with carbon black having thermal stability for hot & cold water supply, capable to withstand temperature up to 80°C, including all special fittings of composite material (engineering plastic blend and brass inserts wherever required) e.g. elbows, tees, reducers, couplers & connectors etc., with trenching, refilling and testing of joints complete as per direction of the engineer in charge. External work 1620 (20 mm OD ) pipe) is derived from 5 priced inputs for 10 metre and works out to ₹289.10 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 30 x P / 100
  • Trenching and refilling etc.
ANALYSIS OF RATES · ITEM 18.3.2DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8301MAT1620 mm PE-AL-PE Composit pressure pipe1620 mm PE-AL-PE Composite pressure pipemetre1067.00670.00
0116LABFitter (grade 1)day0.08897.0071.76
0114LABBeldarday0.16736.00117.76
0114LABBeldarday0.66736.00485.76
0115LABCoolieday0.66736.00485.76
BUILD-UP TO RATE
Add 30% for fittings and wastage etc. on (P)
+201.00
TOTAL
2,032.04
Add 1 % Water charges on “W”
+20.32
TOTAL
2,052.36
Add GST on “X” (multiplying factor 0.2127)
+436.54
TOTAL
2,488.90
Add 15% CPOH on “Y”
+373.34
TOTAL
2,862.24
Add Cess @ 1% on “Z”
+28.62
Cost of 10 metre
2,890.86
Cost of 1 metre
289.09
SAY
₹289.10
D-02/SOURCEPRINTED PAGE 1401
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1401

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1401. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.