CPWD Analysis of Rates · Water Supply
Providing and fixing Polyethelene-AluminiumPolyethelene PE-AL-PE Composite Pressure Pipes conforming to IS - 15450, U.V. stabilized with carbon black having thermal stability for hot & cold water supply, capable to withstand temperature up to 80°C, including all special fittings of composite material (engineering plastic blend and brass inserts wherever required) e.g. elbows, tees, reducers, couplers & connectors etc., with trenching, refilling and testing of joints complete as per direction of the engineer in charge. External work
2532 (32 mm OD ) pipe
- Item number
- 18.3.4
- Analysis basis
- Details of cost for 10 metre
- Priced inputs
- 5
- Derived rate
- ₹435.20 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.3.4 — Providing and fixing Polyethelene-AluminiumPolyethelene PE-AL-PE Composite Pressure Pipes conforming to IS - 15450, U.V. stabilized with carbon black having thermal stability for hot & cold water supply, capable to withstand temperature up to 80°C, including all special fittings of composite material (engineering plastic blend and brass inserts wherever required) e.g. elbows, tees, reducers, couplers & connectors etc., with trenching, refilling and testing of joints complete as per direction of the engineer in charge. External work 2532 (32 mm OD ) pipe — is derived from 5 priced inputs for 10 metre and works out to ₹435.20 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 30 x P / 100
- Trenching and refilling etc.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8303 | 2532 mm PE-AL-PE Composit pressure pipe2532 mm PE-AL-PE Composite pressure pipeMaterial | metre | 10 | 146.00 | 1,460.00 |
| 0116 | Fitter (grade 1)Labour | day | 0.08 | 897.00 | 71.76 |
| 0114 | BeldarLabour | day | 0.16 | 736.00 | 117.76 |
| 0114 | BeldarLabour | day | 0.66 | 736.00 | 485.76 |
| 0115 | CoolieLabour | day | 0.66 | 736.00 | 485.76 |
- Add 30% for fittings and wastage etc. on (P)
- 438.00
- TOTAL
- 3,059.04
- Add 1 % Water charges on “W”
- 30.59
- TOTAL
- 3,089.63
- Add GST on “X” (multiplying factor 0.2127)
- 657.16
- TOTAL
- 3,746.79
- Add 15% CPOH on “Y”
- 562.02
- TOTAL
- 4,308.81
- Add Cess @ 1% on “Z”
- 43.09
- Cost of 10 metre
- 4,351.90
- Cost of 1 metre
- 435.19
- Say
- 435.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1402. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works