Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536

450 mm dia pipe
Item number
18.27.9
Analysis basis
10 metre
Priced inputs
2
Derived rate
₹11,714.85/ METRE
D-01/RATE ANALYSISITEM 18.27.9

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.27.9 (Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536 : 450 mm dia pipe) is derived from 2 priced inputs for 10 metre and works out to ₹11,714.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 450mm dia. spun iron pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 151.270 Kg
  • Weight of 10m pipes 151.270x10 =
  • 1512.70 Kg
ANALYSIS OF RATES · ITEM 18.27.9DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7705MATS&S Centrifugally (Spun) C.I. Pipe class LA 450mm diaS&S Centrifugally (Spun) C.I. Pipe class LA 450 mm diametre107,850.0078,500.00
SUBRate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23quintal15.13361.655,471.76
BUILD-UP TO RATE
TOTAL
83,971.76
Add 1 % Water charges on “W-A”
+785.00
TOTAL
84,756.76
Add GST on “X-A” (multiplying factor 0.2127)
+16,863.92
TOTAL
1,01,620.68
Add 15% CPOH on “Y-A”
+14,422.34
TOTAL
1,16,043.02
Add Cess @ 1% on “Z-A”
+1,105.71
Cost for 10 metre
1,17,148.73
Cost of one metre
11,714.87
SAY
₹11,714.85
D-02/SOURCEPRINTED PAGE 1454
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1454

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1454. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.