Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536

400 mm dia pipe
Item number
18.27.8
Analysis basis
10 metre
Priced inputs
2
Derived rate
₹9,701.00/ METRE
D-01/RATE ANALYSISITEM 18.27.8

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.27.8 (Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536 : 400 mm dia pipe) is derived from 2 priced inputs for 10 metre and works out to ₹9,701.00 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 400mm dia. spun iron pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 125.45 Kg
  • Weight of 10m pipes 125.45x10 = 1254.50
  • Kg
ANALYSIS OF RATES · ITEM 18.27.8DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7704MATS&S Centrifugally (Spun) C.I. Pipe class LA 400mm diaS&S Centrifugally (Spun) C.I. Pipe class LA 400 mm diametre106,500.0065,000.00
SUBRate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23quintal12.55361.654,538.71
BUILD-UP TO RATE
TOTAL
69,538.71
Add 1 % Water charges on “W-A”
+650.00
TOTAL
70,188.71
Add GST on “X-A” (multiplying factor 0.2127)
+13,963.76
TOTAL
84,152.47
Add 15% CPOH on “Y-A”
+11,942.06
TOTAL
96,094.53
Add Cess @ 1% on “Z-A”
+915.56
Cost of 10 metre
97,010.09
Cost of one metre
9,701.01
SAY
₹9,701.00
D-02/SOURCEPRINTED PAGE 1453
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1453

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1453. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.