Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536

350 mm dia pipe
Item number
18.27.7
Analysis basis
10 metre
Priced inputs
2
Derived rate
₹7,343.80/ METRE
D-01/RATE ANALYSISITEM 18.27.7

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.27.7 (Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536 : 350 mm dia pipe) is derived from 2 priced inputs for 10 metre and works out to ₹7,343.80 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 350mm dia. spun iron pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 103.10 Kg
  • Weight of 10m pipes 103.10x10 = 1031.00
  • Kg
ANALYSIS OF RATES · ITEM 18.27.7DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7703MATS&S Centrifugally (Spun) C.I. Pipe class LA 350mm diaS&S Centrifugally (Spun) C.I. Pipe class LA 350 mm diametre104,900.0049,000.00
SUBRate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23quintal10.31361.653,728.61
BUILD-UP TO RATE
TOTAL
52,728.61
Add 1 % Water charges on “W-A”
+490.00
TOTAL
53,218.61
Add GST on “X-A” (multiplying factor 0.2127)
+10,526.52
TOTAL
63,745.13
Add 15% CPOH on “Y-A”
+9,002.48
TOTAL
72,747.61
Add Cess @ 1% on “Z-A”
+690.19
Cost of 10 metre
73,437.80
Cost of one metre
7,343.78
SAY
₹7,343.80
D-02/SOURCEPRINTED PAGE 1453
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1453

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1453. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.