Skip to main content

CPWD Analysis of Rates · Water Supply

Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536

500 mm dia pipe

Item number
18.27.10
Analysis basis
Details of cost for 10 metre
Priced inputs
2
Derived rate
13,728.75 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.27.10 Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536 : 500 mm dia pipe — is derived from 2 priced inputs for 10 metre and works out to ₹13,728.75 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 500mm dia. spun iron pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 177.090 Kg
  • Weight of 10m pipes 177.090x10 =
  • 1770.90 Kg
CodeInputUnitQuantityRate (INR)Amount (INR)
7706S&S Centrifugally (Spun) C.I. Pipe class LA 500mm diaS&S Centrifugally (Spun) C.I. Pipe class LA 500 mm diaMaterialmetre109,200.0092,000.00
Rate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23Sub-analysisquintal17.71361.656,404.82
TOTAL
98,404.82
Add 1 % Water charges on “W-A”
920.00
TOTAL
99,324.82
Add GST on “X-A” (multiplying factor 0.2127)
19,764.08
TOTAL
1,19,088.90
Add 15% CPOH on “Y-A”
16,902.61
TOTAL
1,35,991.51
Add Cess @ 1% on “Z-A”
1,295.87
Cost of 10 metre
1,37,287.38
Cost of one metre
13,728.74
Say
13,728.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1454. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works