Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536

500 mm dia pipe
Item number
18.27.10
Analysis basis
10 metre
Priced inputs
2
Derived rate
₹13,728.75/ METRE
D-01/RATE ANALYSISITEM 18.27.10

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.27.10 (Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536 : 500 mm dia pipe) is derived from 2 priced inputs for 10 metre and works out to ₹13,728.75 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 500mm dia. spun iron pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 177.090 Kg
  • Weight of 10m pipes 177.090x10 =
  • 1770.90 Kg
ANALYSIS OF RATES · ITEM 18.27.10DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7706MATS&S Centrifugally (Spun) C.I. Pipe class LA 500mm diaS&S Centrifugally (Spun) C.I. Pipe class LA 500 mm diametre109,200.0092,000.00
SUBRate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23quintal17.71361.656,404.82
BUILD-UP TO RATE
TOTAL
98,404.82
Add 1 % Water charges on “W-A”
+920.00
TOTAL
99,324.82
Add GST on “X-A” (multiplying factor 0.2127)
+19,764.08
TOTAL
1,19,088.90
Add 15% CPOH on “Y-A”
+16,902.61
TOTAL
1,35,991.51
Add Cess @ 1% on “Z-A”
+1,295.87
Cost of 10 metre
1,37,287.38
Cost of one metre
13,728.74
SAY
₹13,728.75
D-02/SOURCEPRINTED PAGE 1454
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1454

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1454. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.