CPWD Analysis of Rates · Water Supply

Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536

600 mm dia pipe

Item number
18.27.11
Analysis basis
Details of cost for 10 metre
Priced inputs
2
Derived rate
18,636.45 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.27.11 Providing and laying S&S centrifugally cast (spun) iron pipes (Class LA) conforming to IS - 1536 : 600 mm dia pipe — is derived from 2 priced inputs for 10 metre and works out to ₹18,636.45 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 600mm dia. spun iron pipes (in 5.5 m
  • lengths)
  • Weight of 1 m pipes = 236.000 Kg
  • Weight of 10m pipes 236.000x10 =
  • 2360.00 Kg
CodeInputUnitQuantityRate (INR)Amount (INR)
7707S&S Centrifugally (Spun) C.I. Pipe class LA 600mm diaS&S Centrifugally (Spun) C.I. Pipe class LA 600 mm diaMaterialmetre1012,500.001,25,000.00
Rate same as per item no 18.23 of SH: Water SupplyRate as per item 18.23Sub-analysisquintal23.6361.658,534.94
TOTAL
1,33,534.94
Add 1 % Water charges on “W-A”
1,250.00
TOTAL
1,34,784.94
Add GST on “X-A” (multiplying factor 0.2127)
26,853.38
TOTAL
1,61,638.32
Add 15% CPOH on “Y-A”
22,965.51
TOTAL
1,84,603.83
Add Cess @ 1% on “Z-A”
1,760.69
Cost of 10 metre
1,86,364.52
Cost of 1 metre
18,636.45
Say
18,636.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1455. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.