Providing lead caulked joints to spun iron or C.I. pipes and specials, including testing of joints but excluding the cost of pig lead
- Item number
- 18.28.1
- Analysis basis
- 10 joints
- Priced inputs
- 8
- Derived rate
- ₹496.40/ JOINTS
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.28.1 (Providing lead caulked joints to spun iron or C.I. pipes and specials, including testing of joints but excluding the cost of pig lead : 100 mm diameter pipe) is derived from 8 priced inputs for 10 joints and works out to ₹496.40 per joints after water charges, GST, CPOH and cess. The full build-up is below.
- 0.17x 10 =1.70 kg
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1881 | MAT | Spun yarn | kilogram | 1.7 | 61.00 | 103.70 |
| 0761 | MAT | Fuel wood | quintal | 0.28 | 550.00 | 154.00 |
| 0771 | MAT | Kerosene oil | litre | 0.38 | 50.00 | 19.00 |
| 9999 | MAT | Sundries | L.S. | 6.76 | 2.27 | 15.35 |
| 9977 | MAT | Carriage of materials | L.S. | 5.33 | 2.27 | 12.10 |
| 0116 | LAB | Fitter (grade 1) | day | 1 | 897.00 | 897.00 |
| 0117 | LAB | Assistant Fitter or 2nd class Fitter | day | 1 | 816.00 | 816.00 |
| 0114 | LAB | Beldar | day | 2 | 736.00 | 1,472.00 |
- TOTAL
- 3,489.15
- Add 1 % Water charges on “W”
- +34.89
- TOTAL
- 3,524.04
- Add GST on “X” (multiplying factor 0.2127)
- +749.56
- TOTAL
- 4,273.60
- Add 15% CPOH on “Y”
- +641.04
- TOTAL
- 4,914.64
- Add Cess @ 1% on “Z”
- +49.15
- Cost of 10 joints
- 4,963.79
- Cost of one joint
- 496.38
- SAY
- ₹496.40
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1455
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1455. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.