Skip to main content
R/DAR 2023

Providing lead caulked joints to spun iron or C.I. pipes and specials, including testing of joints but excluding the cost of pig lead

100 mm diameter pipe
Item number
18.28.1
Analysis basis
10 joints
Priced inputs
8
Derived rate
₹496.40/ JOINTS
D-01/RATE ANALYSISITEM 18.28.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.28.1 (Providing lead caulked joints to spun iron or C.I. pipes and specials, including testing of joints but excluding the cost of pig lead : 100 mm diameter pipe) is derived from 8 priced inputs for 10 joints and works out to ₹496.40 per joints after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 0.17x 10 =1.70 kg
ANALYSIS OF RATES · ITEM 18.28.1DETAILS OF COST FOR 10 JOINTS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1881MATSpun yarnkilogram1.761.00103.70
0761MATFuel woodquintal0.28550.00154.00
0771MATKerosene oillitre0.3850.0019.00
9999MATSundriesL.S.6.762.2715.35
9977MATCarriage of materialsL.S.5.332.2712.10
0116LABFitter (grade 1)day1897.00897.00
0117LABAssistant Fitter or 2nd class Fitterday1816.00816.00
0114LABBeldarday2736.001,472.00
BUILD-UP TO RATE
TOTAL
3,489.15
Add 1 % Water charges on “W”
+34.89
TOTAL
3,524.04
Add GST on “X” (multiplying factor 0.2127)
+749.56
TOTAL
4,273.60
Add 15% CPOH on “Y”
+641.04
TOTAL
4,914.64
Add Cess @ 1% on “Z”
+49.15
Cost of 10 joints
4,963.79
Cost of one joint
496.38
SAY
₹496.40
D-02/SOURCEPRINTED PAGE 1455
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1455

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1455. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWATER SUPPLY
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.